Overall Project Status

Status Date Overall Project Status Project Officer Contact
26 Jun 2024 Package 1 - 70 %. Total pipe laid - 31 km. Total number of geotagged connections -4519nos. FHTC- 4313, HTC -206 nos. Package 2 - 29%.Pipe laying except Eroor Edamon PWD DLP road completed. Package 3 -80%completed. Proposed OHSR at market junction completed .Pipe laying work in progress. Package 4 - 17% completed .Proposed OHSR at elavarankuzhy completed up to plinth beam. Steining of well cum pump house up to second lift completed.Distribution network laying is in progress. Kollam Project Dn AE
30 Apr 2024 Package 1 - 70 %. Total pipe laid - 31 km. Total number of geotagged connections - FHTC- 4291, HTC - 213. Package 2 -Pipe laying work temporarily stopped . Package 3 - Proposed OHSR at market junction - Handrail work started . Package 4 - Proposed OHSR at elavarankuzhy - Levelling work for footing in progress . PCC for intake well foundation completed at ayiranalloor well site . Kollam Project Dn AE
15 Apr 2024 Package 1 - 70 %. Total pipe laid - 31km. Total number of connections - FHTC- 4282, HTC - 176. Package 2 -Pipe laying work temporarily stopped . Package 3 - DI pipe laying work in progress at market junction OHSR site . Proposed OHSR at market junction - Plastering work completed & Painting work of side wall , columns , floor & plinth beam completed . Package 4 - Proposed OHSR at elavarankuzhy - Breaking & levelling work for footing in progress . Blasting & excavation work for intake well progressing at ayiranalloor well site . Kollam Project Dn AE
30 Mar 2024 Package 1 - 69 %. Total number of connections - FHTC- 4282, HTC - 176. Package 2 -Pipe laying work temporarily stopped . Package 3 - Proposed OHSR at market junction - Plastering work completed & Painting work of side wall , columns , floor & plinth beam completed . Package 4 - Proposed OHSR at elavarankuzhy - Breaking & levelling work for footing in progress . Blasting & excavation work for intake well progressing at ayiranalloor well site . Kollam Project Dn AE
15 Mar 2024 Package 1 - 69 %. Total pipe laid - 31km. Total number of connections - FHTC- 4281, HTC - 155. Package 2 -Pipe laying work temporarily stopped . Package 3 - Pipe laying work progressing and Proposed OHSR at market junction - Plastering work completed & Painting work in progress . Package 4 - Pipe laying work progressing . Proposed OHSR at elavarankuzhy - Earth excavation work for footing in progress . Earth excavation work for well started at ayiranalloor well site . Kollam Project Dn AE
29 Feb 2024 Package 1 - 66 %. GI laying work started at Yeroor . Total pipe laid - 30.555km. Total geotagged - FHTC- 4281, HTC - 58. Package 2 -Pipe laying work progressing. Package 3 - Pipe laying work progressing and Proposed OHSR at market junction - Plastering work in progress & Primer work started . Package 4 - Pipe laying work progressing . Proposed OHSR at elavarankuzhy - Earth excavation work for footing in progress . Earth excavation work for well started at ayiranalloor well site . Kollam Project Dn AE
14 Feb 2024 Package 1 - 65 %. GI laying work started at Yeroor . Total pipe laid - 30.555km. Total geotagged - FHTC- 4281, HTC - 58. Package 2 -Pipe laying work progressing. Package 3 - Pipe laying work progressing. and Proposed OHSR at market junction - Plastering work of side wall & columns started . Package 4 - Pipe laying work progressing . Proposed OHSR at elavarankuzhy - Earth excavation work for footing started . Kollam Project Dn AE
26 Jan 2024 Package 1 - 64 %. Total pipe laid - 30.555km. Total geotagged - FHTC- 4281, HTC - 58. Package 2 -Pipe laying work progressing. Package 3 - Pipe laying work progressing. and Proposed OHSR at market junction - Side wall 3rd lift concreting completed. Package 4 - Pipe laying work progressing Kollam Project Dn AE
16 Jan 2024 Package 1 - 64 %. Total pipe laid - 30.555km. Total geotagged - FHTC- 4281, HTC - 58. Package 2 -Pipe laying work progressing. 11730 m laying completed. Package 3 - Pipe laying work progressing. 17525m laying completed and Proposed OHSR at market junction - Floor slab concreting completed. Package 4 - Pipe laying work progressing Kollam Project Dn AE
26 Dec 2023 Package 1 - 64 %. Total pipe laid - 30.555km. Total geotagged - FHTC- 4281, HTC - 58. Package 2 -Pipe laying work progressing. Package 3 - Pipe laying work progressing and Proposed OHSR at market junction - Floor slab concreting completed Kollam Project Dn EE