Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
26 Jun 2024 | Package 1 - 70 %. Total pipe laid - 31 km. Total number of geotagged connections -4519nos. FHTC- 4313, HTC -206 nos. Package 2 - 29%.Pipe laying except Eroor Edamon PWD DLP road completed. Package 3 -80%completed. Proposed OHSR at market junction completed .Pipe laying work in progress. Package 4 - 17% completed .Proposed OHSR at elavarankuzhy completed up to plinth beam. Steining of well cum pump house up to second lift completed.Distribution network laying is in progress. | Kollam Project Dn AE | |
30 Apr 2024 | Package 1 - 70 %. Total pipe laid - 31 km. Total number of geotagged connections - FHTC- 4291, HTC - 213. Package 2 -Pipe laying work temporarily stopped . Package 3 - Proposed OHSR at market junction - Handrail work started . Package 4 - Proposed OHSR at elavarankuzhy - Levelling work for footing in progress . PCC for intake well foundation completed at ayiranalloor well site . | Kollam Project Dn AE | |
15 Apr 2024 | Package 1 - 70 %. Total pipe laid - 31km. Total number of connections - FHTC- 4282, HTC - 176. Package 2 -Pipe laying work temporarily stopped . Package 3 - DI pipe laying work in progress at market junction OHSR site . Proposed OHSR at market junction - Plastering work completed & Painting work of side wall , columns , floor & plinth beam completed . Package 4 - Proposed OHSR at elavarankuzhy - Breaking & levelling work for footing in progress . Blasting & excavation work for intake well progressing at ayiranalloor well site . | Kollam Project Dn AE | |
30 Mar 2024 | Package 1 - 69 %. Total number of connections - FHTC- 4282, HTC - 176. Package 2 -Pipe laying work temporarily stopped . Package 3 - Proposed OHSR at market junction - Plastering work completed & Painting work of side wall , columns , floor & plinth beam completed . Package 4 - Proposed OHSR at elavarankuzhy - Breaking & levelling work for footing in progress . Blasting & excavation work for intake well progressing at ayiranalloor well site . | Kollam Project Dn AE | |
15 Mar 2024 | Package 1 - 69 %. Total pipe laid - 31km. Total number of connections - FHTC- 4281, HTC - 155. Package 2 -Pipe laying work temporarily stopped . Package 3 - Pipe laying work progressing and Proposed OHSR at market junction - Plastering work completed & Painting work in progress . Package 4 - Pipe laying work progressing . Proposed OHSR at elavarankuzhy - Earth excavation work for footing in progress . Earth excavation work for well started at ayiranalloor well site . | Kollam Project Dn AE | |
29 Feb 2024 | Package 1 - 66 %. GI laying work started at Yeroor . Total pipe laid - 30.555km. Total geotagged - FHTC- 4281, HTC - 58. Package 2 -Pipe laying work progressing. Package 3 - Pipe laying work progressing and Proposed OHSR at market junction - Plastering work in progress & Primer work started . Package 4 - Pipe laying work progressing . Proposed OHSR at elavarankuzhy - Earth excavation work for footing in progress . Earth excavation work for well started at ayiranalloor well site . | Kollam Project Dn AE | |
14 Feb 2024 | Package 1 - 65 %. GI laying work started at Yeroor . Total pipe laid - 30.555km. Total geotagged - FHTC- 4281, HTC - 58. Package 2 -Pipe laying work progressing. Package 3 - Pipe laying work progressing. and Proposed OHSR at market junction - Plastering work of side wall & columns started . Package 4 - Pipe laying work progressing . Proposed OHSR at elavarankuzhy - Earth excavation work for footing started . | Kollam Project Dn AE | |
26 Jan 2024 | Package 1 - 64 %. Total pipe laid - 30.555km. Total geotagged - FHTC- 4281, HTC - 58. Package 2 -Pipe laying work progressing. Package 3 - Pipe laying work progressing. and Proposed OHSR at market junction - Side wall 3rd lift concreting completed. Package 4 - Pipe laying work progressing | Kollam Project Dn AE | |
16 Jan 2024 | Package 1 - 64 %. Total pipe laid - 30.555km. Total geotagged - FHTC- 4281, HTC - 58. Package 2 -Pipe laying work progressing. 11730 m laying completed. Package 3 - Pipe laying work progressing. 17525m laying completed and Proposed OHSR at market junction - Floor slab concreting completed. Package 4 - Pipe laying work progressing | Kollam Project Dn AE | |
26 Dec 2023 | Package 1 - 64 %. Total pipe laid - 30.555km. Total geotagged - FHTC- 4281, HTC - 58. Package 2 -Pipe laying work progressing. Package 3 - Pipe laying work progressing and Proposed OHSR at market junction - Floor slab concreting completed | Kollam Project Dn EE |