JAL JEEVAN--MISSION Estimate for providing FHTC in EROOR Grama Panchayath From Existing Scheme and Extension during the period 2020-21
Project |
JAL JEEVAN--MISSION Estimate for providing FHTC in EROOR Grama Panchayath From Existing Scheme and Extension during the period 2020-21 |
Project Code |
KLMJJM08203137 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
JAL JEEVAN--MISSION Estimate for providing FHTC in EROOR Grama Panchayath From Existing Scheme and Extension
during the period 2020-21 |
Status |
On-going |
District |
Kollam |
Executing Office |
Kollam Project Dn |
AS Amount (Rs) |
742000000
|
AS Number |
G.O.(Rt)No.134/2022/WRD Dated,Thiruvananthapuram(Re appropriation AS no.GO(Rt).897/2023/WRD dated.26.10.2023) |
TS Amount (Rs) |
538940000 |
TS Number |
TS/2020-2021/2020/16302 |
Total Bill Submitted (Rs) |
159600952 |
Total Bill Paid (Rs) |
48581805 |
Population Benefitted |
32344 |
Capacity in MLD |
1.78 |
Actual Project Completion Date |
30 Dec 2023 |
Coverage |
yeroor panchayath |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
JAL JEEVAN--Estimate for providing FHTC in EROOR Grama Panchayath From Existing Scheme and Extension during the period 2020-21 |
Kollam Project Dn |
|
2 |
Jal Jeevan Mission (JJM)-Yeroor Phase- I -Package -4 -Construction of Proposed well cum Pumphouse near Ayiranalloor bridge, Sump cum pump house, Pressure filter & 5.5 LL OHSR at Elavaramkuzhy and its associated distribution network |
Kollam Project Dn |
|
3 |
JJM-WSS TO EROOR PANCHAYATH-PHASE-1-PACKAGE -2-LAYING OF PUMPING MAIN&GRAVITY MAIN TO OHSR'S , DISTRIBUTION NETWORK IN ERROR-EDAMON ROAD AND ITS BY ROADS |
Kollam Project Dn |
|
4 |
JJM-WSS to Yeroor-Phase-I- Package-3- Construction of 4.85LL capacity OHSR at Market Junction and laying of distribution network from the OHSR in Eroor Panchayath in Kollam District |
Kollam Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
26 Jun 2024 |
Package 1 - 70 %. Total pipe laid - 31 km. Total number of geotagged connections -4519nos. FHTC- 4313, HTC -206 nos.
Package 2 - 29%.Pipe laying except Eroor Edamon PWD DLP road completed.
Package 3 -80%completed. Proposed OHSR at market junction completed .Pipe laying work in progress.
Package 4 - 17% completed .Proposed OHSR at elavarankuzhy completed up to plinth beam. Steining of well cum pump house up to second lift completed.Distribution network laying is in progress. |
Kollam Project Dn AE |
|
30 Apr 2024 |
Package 1 - 70 %. Total pipe laid - 31 km. Total number of geotagged connections - FHTC- 4291, HTC - 213. Package 2 -Pipe laying work temporarily stopped . Package 3 - Proposed OHSR at market junction - Handrail work started . Package 4 - Proposed OHSR at elavarankuzhy - Levelling work for footing in progress . PCC for intake well foundation completed at ayiranalloor well site . |
Kollam Project Dn AE |
|
15 Apr 2024 |
Package 1 - 70 %. Total pipe laid - 31km. Total number of connections - FHTC- 4282, HTC - 176. Package 2 -Pipe laying work temporarily stopped . Package 3 - DI pipe laying work in progress at market junction OHSR site . Proposed OHSR at market junction - Plastering work completed & Painting work of side wall , columns , floor & plinth beam completed . Package 4 - Proposed OHSR at elavarankuzhy - Breaking & levelling work for footing in progress . Blasting & excavation work for intake well progressing at ayiranalloor well site . |
Kollam Project Dn AE |
|
30 Mar 2024 |
Package 1 - 69 %. Total number of connections - FHTC- 4282, HTC - 176. Package 2 -Pipe laying work temporarily stopped . Package 3 - Proposed OHSR at market junction - Plastering work completed & Painting work of side wall , columns , floor & plinth beam completed . Package 4 - Proposed OHSR at elavarankuzhy - Breaking & levelling work for footing in progress . Blasting & excavation work for intake well progressing at ayiranalloor well site . |
Kollam Project Dn AE |
|
15 Mar 2024 |
Package 1 - 69 %. Total pipe laid - 31km. Total number of connections - FHTC- 4281, HTC - 155. Package 2 -Pipe laying work temporarily stopped . Package 3 - Pipe laying work progressing and Proposed OHSR at market junction - Plastering work completed & Painting work in progress . Package 4 - Pipe laying work progressing . Proposed OHSR at elavarankuzhy - Earth excavation work for footing in progress . Earth excavation work for well started at ayiranalloor well site . |
Kollam Project Dn AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
06/02/2021 |
Scheduled date of Completion of the Project |
30 Jun 2023 |
Expected date of Completion |
30/06/2023 |
Processing Dates
AS Date |
22 Feb 2022 |
TS Date |
04 Sep 2020 |