Overall Project Status

Status Date Overall Project Status Project Officer Contact
26 Apr 2022 FHTC Geotagged-3808 nos(geotagged today=8 nos) FHTC total-3808 Nos(today physical connection-8 nos)Total pipe laid 27.013km Kollam Project Dn AE
25 Apr 2022 FHTC Geotagged-3800 nos(geotagged today= 6 nos) FHTC total-3800 Nos(today physical connection-6 nos)Total pipe laid 26.893km Kollam Project Dn AE
23 Apr 2022 FHTC Geotagged-3794 nos(geotagged today= 9 nos) FHTC total-3794 Nos(today physical connection-9 nos)Total pipe laid 26.893km Kollam Project Dn AE
22 Apr 2022 FHTC Geotagged-3785 nos(geotagged today= 9 nos) FHTC total-3785 Nos(today physical connection-9 nos)Total pipe laid 26.893km Kollam Project Dn AE
21 Apr 2022 FHTC Geotagged-3776 nos(geotagged today= 5 nos) FHTC total-3776 Nos(today physical connection-5 nos)Total pipe laid 26.758km Kollam Project Dn AE
20 Apr 2022 FHTC Geotagged-3771 nos(geotagged today= 6 nos) FHTC total-3771 Nos(today physical connection-6 nos)Total pipe laid 26.608km Kollam Project Dn AE
19 Apr 2022 FHTC Geotagged-3765 nos(geotagged today= 4 nos) FHTC total-3765 Nos(today physical connection-4 nos)Total pipe laid 26.608km Kollam Project Dn AE
18 Apr 2022 FHTC Geotagged-3761 nos(geotagged today= 6 nos) FHTC total-3761 Nos(today physical connection-6 nos)Total pipe laid 26.608km Kollam Project Dn AE
16 Apr 2022 FHTC Geotagged-3755 nos(geotagged today= 8 nos) FHTC total-3755 Nos(today physical connection-8 nos)Total pipe laid 26.508km Kollam Project Dn AE
15 Apr 2022 FHTC Geotagged-3747 nos(geotagged today= 0 nos) FHTC total-3747 Nos(today physical connection-0 nos)Total pipe laid 26.5058km Kollam Project Dn AE