Status Date |
Overall Project Status |
Project Officer |
Contact |
05 Aug 2022 |
Package 1- 61% work completed, FHTC Geotagged-4091 nos, FHTC total-4091 Nos, Total pipe laid 28.563km. Package 2 - Selection notice issued on 15/7/2022. Package 3 - Tender; Submission date:7.6.22, Opening date:9.6.22, NO offer received |
Kollam Project Dn AE |
|
02 Aug 2022 |
Package 1- 61% work completed, FHTC Geotagged-4091 nos, FHTC total-4091 Nos, Total pipe laid 28.563km. Package 2 - Selection notice issued on 15/7/2022. Package 3 - Tender; Submission date:7.6.22, Opening date:9.6.22, NO offer received |
Kollam Project Dn AE |
|
01 Aug 2022 |
Package 1- 61% work completed, FHTC Geotagged-4091 nos, FHTC total-4091 Nos, Total pipe laid 28.563km. Package 2 - Selection notice issued on 15/7/2022. Package 3 - Tender; Submission date:7.6.22, Opening date:9.6.22, NO offer received |
Kollam Project Dn AE |
|
30 Jul 2022 |
Package 1- 61% work completed, FHTC Geotagged-4090 nos, FHTC total-4090 Nos, Total pipe laid 28.563km. Package 2 - Selection notice issued on 15/7/2022. Package 3 - Tender; Submission date:7.6.22, Opening date:9.6.22, NO offer received |
Kollam Project Dn AE |
|
28 Jul 2022 |
Package 1- 61% work completed, FHTC Geotagged-4090 nos, FHTC total-4090 Nos, Total pipe laid 28.563km. Package 2 - Selection notice issued on 15/7/2022. Package 3 - Tender; Submission date:7.6.22, Opening date:9.6.22, NO offer received |
Kollam Project Dn AE |
|
26 Jul 2022 |
Package 1- 61% work completed, FHTC Geotagged-4090 nos, FHTC total-4090 Nos, Total pipe laid 28.563km. Package 2 - Selection notice issued on 15/7/2022. Package 3 - Tender; Submission date:7.6.22, Opening date:9.6.22, NO offer received |
Kollam Project Dn AE |
|
25 Jul 2022 |
Package 1- 61% work completed, FHTC Geotagged-4090 nos, FHTC total-4090 Nos, Total pipe laid 28.563km. Package 2 - Selection notice issued on 15/7/2022. Package 3 - Tender; Submission date:7.6.22, Opening date:9.6.22, NO offer received |
Kollam Project Dn AE |
|
21 Jul 2022 |
Package 1- 61% work completed, FHTC Geotagged-4090 nos, FHTC total-4090 Nos, Total pipe laid 28.563km. Package 2 - Selection notice under processing. Package 3 - Tender; Submission date:7.6.22, Opening date:9.6.22, NO offer received |
Kollam Project Dn AE |
|
19 Jul 2022 |
Package 1- 61% work completed, FHTC Geotagged-4079 nos( geotagged today=06nos) FHTC total-4079 Nos (today physical connection- 6 nos)Total pipe laid 28.563km. Package 2 - Selection notice under processing. Package 3 - Tender; Submission date:7.6.22, Opening date:9.6.22, NO offer received |
Kollam Project Dn AE |
|
16 Jul 2022 |
Package 1- 61% work completed, FHTC Geotagged-4073 nos( geotagged today=0 nos) FHTC total-4073 Nos (today physical connection- 0 nos)Total pipe laid 28.563km. Package 2 - Selection notice under processing. Package 3 - Tender; Submission date:7.6.22, Opening date:9.6.22, NO offer received |
Kollam Project Dn AE |
|