Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
30 Nov 2023 | Package 1 - 64 %. Total pipe laid - 30.555km. Total geotagged - FHTC- 4281, HTC - 58. Package 2 -Pipe laying work progressing. Package 3 - Pipe laying work progressing and Proposed OHSR at market junction - work progressing (Colum concreting completed- 1.5m 1st lift and 1.5m 2nd lift) | Kollam Project Dn EE | |
04 Nov 2023 | Package 1 - 64 %. Total pipe laid - 30.555km. Total geotagged - FHTC- 4281, HTC - 58. Package 2 -Pipe laying work progressing. Package 3 - Pipe laying work progressing and Proposed OHSR at market junction - work progressing | Kollam Project Dn AE | |
02 Sep 2023 | Package 1 - 64 %. FHTC Geotagged - 4281 nos, HTC Geotagged - 58 nos, Total pipe laid - 30.555km. Package 2 -Pipe laying work progressing. Package 3 - work started | Kollam Project Dn AE | |
05 Aug 2023 | Package 1 - 64 %. FHTC Geotagged - 4281 nos, HTC Geotagged - 58 nos, Total pipe laid - 30.555km. Package 2 -Agreement executed. Package 3 - Laying in progress | Kollam Project Dn AE | |
21 Jun 2023 | Package 1 - 64 %. FHTC Geotagged - 4277 nos, HTC Geotagged - 58 nos, Total pipe laid - 30.555km. Package 2 -First tender cancelled due to technical reasons by SE, PH circle, Kollam. Retender invited with due date 11.05.2023 and opened on 12.05.2023. 2 offers recieved. Package 3 - PVC and DI pipe(Part) supplied ,laying in progress | Kollam Project Dn EE | |
11 Apr 2023 | Package 1 - 64 %. FHTC Geotagged - 4261 nos, HTC Geotagged - 58 nos, Total pipe laid - 30.555km. Package 2 -TS approved, Bid preparation stage. Package 3 - Agreement executed, Pipe supply started | Kollam Project Dn EE | |
24 Mar 2023 | Package 1 - 64 %. FHTC Geotagged - 4243 nos, HTC Geotagged - 58 nos, Total pipe laid - 30.555km. Package 2 -TS approved, Bid preparation stage. Package 3 - Agreement executed | Kollam Project Dn EE | |
19 Jan 2023 | Package 1 - 64 %. FHTC Geotagged - 4260 nos, FHTC total - 4260 Nos, Total pipe laid - 30.555km. Package 2 -Selection notice under processing. Package 3 - Estimate submitted to higher authority for TS. | Kollam Project Dn AE | |
18 Jan 2023 | Package 1 - 64 %. FHTC Geotagged - 4260 nos, FHTC total - 4260 Nos, Total pipe laid - 30.555km. Package 2 -Selection notice under processing. Package 3 - Estimate submitted to higher authority for TS. | Kollam Project Dn AE | |
17 Jan 2023 | Package 1 - 64 %. FHTC Geotagged - 4260 nos, FHTC total - 4260 Nos, Total pipe laid - 30.555km. Package 2 -Selection notice under processing. Package 3 - OHSR Structural drawing approved by WASCON. Estimate submitted in Price 3. | Kollam Project Dn AE |