Status Date |
Overall Project Status |
Project Officer |
Contact |
05 Dec 2022 |
Package 1 - 64 %. FHTC Geotagged - 4252 nos, FHTC total - 4252 Nos, Total pipe laid - 30.555km. Package 2 -Single offer recieved on tender due on 25/11/2022. Work retendered with due date 19/12/2022. Package 3 - Tank design submitted to WASCON for approval. |
Kollam Project Dn AE |
|
02 Dec 2022 |
Package 1 - 64 %. FHTC Geotagged - 4252 nos, FHTC total - 4252 Nos, Total pipe laid - 30.555km. Package 2 -Single offer recieved on tender due on 25/11/2022. Work retendered with due date 19/12/2022. Package 3 - Tank design submitted to WASCON for approval. |
Kollam Project Dn AE |
|
01 Dec 2022 |
Package 1 - 64 %. FHTC Geotagged - 4251 nos, FHTC total - 4251 Nos, Total pipe laid - 30.555km. Package 2 -Single offer recieved on tender due on 25/11/2022. Work retendered with due date 19/12/2022. Package 3 - Tank design submitted to WASCON for approval. |
Kollam Project Dn AE |
|
30 Nov 2022 |
Package 1 - 64 %. FHTC Geotagged - 4251 nos, FHTC total - 4251 Nos, Total pipe laid - 30.555km. Package 2 -Single offer recieved on tender due on 25/11/2022. Work retendered with due date 19/12/2022. Package 3 - Tank design submitted to WASCON for approval. |
Kollam Project Dn AE |
|
17 Oct 2022 |
Package 1 - 64 %. FHTC - 4212Nos. Package 2 -As per direction new price 3 estimate submitted on 17/10/2022. Package 3 - Land handed over by Panchayath authorities. Soil investigation conducted, awaiting report |
Kollam Project Dn AE |
|
06 Oct 2022 |
Package 1 - 63 %. FHTC - 4192Nos. Package 2 -Contractor disagreed to execute work at 8.11 % above estimate rate ie at LMR rate. The LMR justification estimate in PRICE 3.0 is 18.39 % above tendered PAC (ie as per PRICE 1.0). This proposal submitted to CE(CR) for tender approval. Package 3 - Land handed over by Panchayath authorities. Soil investigation conducted, awaiting report |
Kollam Project HD |
|
17 Sep 2022 |
Package 1 - 63 %. FHTC - 4172 Nos.
Package 2 - Contractor disagreed to execute work at 8.11 % above estimate rate ie at LMR rate. The LMR justification estimate in PRICE 3.0 is 18.39 % above tendered PAC (ie as per PRICE 1.0). This proposal submitted to CE(CR) for tender approval.
Package 3 - Land not handed over to KWA. |
Kollam Project HD |
|
01 Sep 2022 |
Package 1- 62%work completed, FHTC Geotagged-4162 nos, FHTC total- 4162 Nos, Total pipe laid 29.710km. Package 2 - Selection notice issued on 15/7/2022. Package 3 - Land for the OHSR not handed over to KWA |
Kollam Project Dn AE |
|
20 Aug 2022 |
Package 1- 62%work completed, FHTC Geotagged-4148 nos, FHTC total-4148 Nos, Total pipe laid 29.710km. Package 2 - Selection notice issued on 15/7/2022. Package 3 - Tender; Submission date:7.6.22, Opening date:9.6.22, NO offer received |
Kollam Project Dn AE |
|
09 Aug 2022 |
Package 1- 61% work completed, FHTC Geotagged-4091 nos, FHTC total-4091 Nos, Total pipe laid 28.563km. Package 2 - Selection notice issued on 15/7/2022. Package 3 - Tender; Submission date:7.6.22, Opening date:9.6.22, NO offer received |
Kollam Project Dn AE |
|