| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 14 Nov 2024 | 2250 meter pipe laid out of 3250 meter and work ongoing. | Kollam WS Sn 2 - AE | |
| 11 Nov 2024 | 2141.3m Pipe laid. Work in progress | Kollam WS Sn 2 - AE | |
| 05 Nov 2024 | 2141.3m Pipe laid. Work in progress | Kollam WS Sn 2 - AE | |
| 02 Nov 2024 | Work in progress | Kollam WS Sn 2 - AE | |
| 30 Oct 2024 | Work in progress | Kollam WS Sn 2 - AE | |
| 28 Oct 2024 | Intermittent heavy rain causes water logged in most of the pipe laying area and affects the progress of work. | Kollam WS Sn 2 - AE | |
| 25 Oct 2024 | Work delaying due to water logging and heavy rainfall | Kollam WS Sn 2 - AE | |
| 22 Oct 2024 | Work delaying due to water logging | Kollam WS Sn 2 - AE | |
| 18 Oct 2024 | Work in progress | Kollam WS Sn 2 - AE | |
| 14 Oct 2024 | Work in progress | Kollam WS Sn 2 - AE |