Overall Project Status

Status Date Overall Project Status Project Officer Contact
14 Nov 2024 2250 meter pipe laid out of 3250 meter and work ongoing. Kollam WS Sn 2 - AE
11 Nov 2024 2141.3m Pipe laid. Work in progress Kollam WS Sn 2 - AE
05 Nov 2024 2141.3m Pipe laid. Work in progress Kollam WS Sn 2 - AE
02 Nov 2024 Work in progress Kollam WS Sn 2 - AE
30 Oct 2024 Work in progress Kollam WS Sn 2 - AE
28 Oct 2024 Intermittent heavy rain causes water logged in most of the pipe laying area and affects the progress of work. Kollam WS Sn 2 - AE
25 Oct 2024 Work delaying due to water logging and heavy rainfall Kollam WS Sn 2 - AE
22 Oct 2024 Work delaying due to water logging Kollam WS Sn 2 - AE
18 Oct 2024 Work in progress Kollam WS Sn 2 - AE
14 Oct 2024 Work in progress Kollam WS Sn 2 - AE