| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 29 Jul 2024 | Heavy rainfall delaying the progress of work | Kollam WS Sn 2 - AE | |
| 25 Jul 2024 | Work in progress | Kollam WS Sn 2 - AE | |
| 22 Jul 2024 | Heavy rainfall delaying the progress of work | Kollam WS Sn 2 - AE | |
| 18 Jul 2024 | Heavy rain affects the progress of work | Kollam WS Sn 2 - AE | |
| 12 Jul 2024 | Work in progress | Kollam WS Sn 2 - AE | |
| 09 Jul 2024 | Work in progress | Kollam WS Sn 2 - AE | |
| 05 Jul 2024 | Work in progress | Kollam WS Sn 2 - AE | |
| 02 Jul 2024 | Due to heavy rain and water logging in the Project area work progress is Nil. | Kollam WS Sn 2 - AE | |
| 29 Jun 2024 | Due to heavy rain and water logging in the Project area work progress is Nil. | Kollam WS Sn 2 - AE | |
| 26 Jun 2024 | Due to heavy rain and water logging in the Project area work progress is Nil. | Kollam WS Sn 2 - AE |