- Home
- AMRUT 2.0 Retrofitting Balance work supp...
AMRUT 2.0 Retrofitting Balance work supplying & laying 90/75/63 mm pvc pipeline for providing house connection (FHTCs) -pipeline work WSS 2
| Project |
AMRUT 2.0 Retrofitting Balance work supplying & laying 90/75/63 mm pvc pipeline for providing house connection (FHTCs) -pipeline work WSS 2 |
| Project Code |
KLMAMRUT 2112215324 |
| Type |
Main project |
| Funding Agency |
AMRUT 2 |
| Category |
AMRUT 2 |
| Type of scheme |
Water Supply |
| Scheme |
|
| Description |
AMRUT 2.0 Retrofitting Balance work supplying & laying 90/75/63 mm pvc pipeline for providing house connection (FHTCs) -pipeline work (section 2) |
| Status |
Completed |
| District |
Kollam |
| Executing Office |
Kollam WS Sn 2 |
| AS Amount (Rs) |
222200000
|
| AS Number |
G. O (Rt)No.2906/2022/LSGD |
| TS Amount (Rs) |
5816400 |
| TS Number |
WRD/KW-CE(SR)/TS/12805/2023_26_1_1 |
| Total Bill Submitted (Rs) |
2835240 |
| Total Bill Paid (Rs) |
0 |
| Population Benefitted |
40350 |
| Capacity in MLD |
11.00 |
| Actual Project Completion Date |
21 Jun 2025 |
| Coverage |
55 Divisions in Kollam corporation. |
| Implementation Schedule |
Download |
| Work Plan |
Download |
Packages
| No. |
Project Name |
Location |
View |
| 1 |
AMRUT 2.0 Retrofitting Balance work supplying & laying 90/75/63 mm pvc pipeline for providing house connection (FHTCs) -pipeline work |
Kollam WS Sn 2 |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 19 Jan 2026 |
Work completed and final bill submitted on 19.12.2025 |
Kollam WS Sn 2 - AE |
|
| 18 Nov 2025 |
Pipe laying work successfully completed, but concrete restoration in small portion pending due to heavy rain. |
Kollam WS Sn 2 - AE |
|
| 01 Sep 2025 |
Pipe laying work successfully completed, but concrete restoration in small portion pending due to heavy rain. |
Kollam WS Sn 2 - AE |
|
| 01 Aug 2025 |
Pipe laying work successfully completed, but concrete restoration in small portion pending due to heavy rain. |
Kollam WS Sn 2 - AE |
|
| 08 Jul 2025 |
Pipe laying work successfully completed, but concrete restoration in small portion pending due to heavy rain. |
Kollam WS Sn 2 - AE |
|
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
07/12/2023 |
| Scheduled date of Completion of the Project |
06 Jun 2024 |
| Expected date of Completion |
08/07/2024 |
Processing Dates
| AS Date |
24 Nov 2022 |
| TS Date |
13 Jul 2023 |