| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 06 Feb 2025 | Pipe laying completed, and restoration of concrete to be completed, progress of work is slow due to the lack of workers. | Kollam WS Sn 2 - AE | |
| 03 Feb 2025 | Pipe laying completed, and restoration of concrete to be completed, progress of work is slow due to the lack of workers. | Kollam WS Sn 2 - AE | |
| 30 Jan 2025 | Pipe laying completed, and restoration of concrete to be completed, progress of work is slow due to the lack of workers. | Kollam WS Sn 2 - AE | |
| 28 Jan 2025 | Pipe laying completed, and restoration of concrete is in progress. | Kollam WS Sn 2 - AE | |
| 24 Jan 2025 | Pipe laying completed, and restoration of concrete is in progress. | Kollam WS Sn 2 - AE | |
| 21 Jan 2025 | Pipe laying completed, and restoration of concrete is in progress. | Kollam WS Sn 2 - AE | |
| 14 Jan 2025 | 2950 m ouot of 3250 m completed, and restoration of concrete is in progress. | Kollam WS Sn 2 - AE | |
| 14 Jan 2025 | Pipe laying is ongoing . | Kollam WS Sn 2 - AE | |
| 13 Jan 2025 | 2698.70 meter pipe laid out of 3250 meter and work ongoing | Kollam WS Sn 2 - AE | |
| 06 Jan 2025 | 2698.70 meter pipe laid out of 3250 meter and work ongoing | Kollam WS Sn 2 - AE |