| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 01 Jan 2025 | 2698.70 meter pipe laid out of 3250 meter and work ongoing | Kollam WS Sn 2 - AE | |
| 26 Dec 2024 | 2698.70 meter pipe laid out of 3250 meter and work ongoing | Kollam WS Sn 2 - AE | |
| 21 Dec 2024 | 2698.70 meter pipe laid out of 3250 meter and work ongoing | Kollam WS Sn 2 - AE | |
| 16 Dec 2024 | 2698.70 meter pipe laid out of 3250 meter and work ongoing | Kollam WS Sn 2 - AE | |
| 09 Dec 2024 | 2698.70 meter pipe laid out of 3250 meter and work ongoing | Kollam WS Sn 2 - AE | |
| 04 Dec 2024 | Work progressing | Kollam WS Sn 2 - AE | |
| 30 Nov 2024 | Work progressing | Kollam WS Sn 2 - AE | |
| 28 Nov 2024 | 2698.70 meter pipe laid out of 3250 meter and work ongoing | Kollam WS Sn 2 - AE | |
| 25 Nov 2024 | 2648.7 meter pipe laid out of 3250 meter and work ongoing | Kollam WS Sn 2 - AE | |
| 20 Nov 2024 | 2250 meter pipe laid out of 3250 meter and work ongoing | Kollam WS Sn 2 - AE |