| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 19 Jun 2024 | Work in progress | Kollam WS Sn 2 - AE | |
| 15 Jun 2024 | Work in progress | Kollam WS Sn 2 - AE | |
| 14 Jun 2024 | Work in progress | Kollam WS Sn 2 - AE | |
| 10 Jun 2024 | Due to frequent heavy rain work progress is slow. | Kollam WS Sn 2 - AE | |
| 05 Jun 2024 | Due to heavy water logged and land sliding area , pipe laying is difficult. | Kollam WS Sn 2 - AE | |
| 01 Jun 2024 | Due to heavy and continuous rain work not possible | Kollam WS Sn 2 - AE | |
| 28 May 2024 | Due to heavy and continuous rain work not possible | Kollam WS Sn 2 - AE | |
| 25 May 2024 | Due to heavy and continuous rain work not possible | Kollam WS Sn 2 - AE | |
| 21 May 2024 | Pipe laying work is ongoing . Heavy rain affects the progress of the work. | Kollam WS Sn 2 - AE | |