Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
26 Mar 2025 Pipe laying completed, and restoration of concrete to be completed, progress of work is slow due to the lack of workers from contractor side. Kollam WS Sn 2 - AE
22 Mar 2025 Pipe laying completed, and restoration of concrete to be completed, progress of work is slow due to the lack of workers from contractor side. Kollam WS Sn 2 - AE
18 Mar 2025 Pipe laying completed, and restoration of concrete to be completed, progress of work is slow due to the lack of workers from contractor side. Kollam WS Sn 2 - AE
14 Mar 2025 Pipe laying completed, and restoration of concrete to be completed, progress of work is slow due to the lack of workers from contractor side Kollam WS Sn 2 - AE
11 Mar 2025 Pipe laying completed, and restoration of concrete to be completed, progress of work is slow due to the lack of workers from contractor side Kollam WS Sn 2 - AE
06 Mar 2025 Pipe laying completed, and restoration of concrete to be completed, progress of work is slow due to the lack of workers from contractor side Kollam WS Sn 2 - AE
27 Feb 2025 Pipe laying completed, and restoration of concrete to be completed, progress of work is slow due to the lack of workers from contractor side Kollam WS Sn 2 - AE
22 Feb 2025 Pipe laying completed, and restoration of concrete to be completed, progress of work is slow due to the lack of workers from contractor side Kollam WS Sn 2 - AE
15 Feb 2025 Pipe laying completed, and restoration of concrete to be completed, progress of work is slow due to the lack of workers. Kollam WS Sn 2 - AE
10 Feb 2025 Pipe laying completed, and restoration of concrete to be completed, progress of work is slow due to the lack of workers. Kollam WS Sn 2 - AE