Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
28 Apr 2023 | Pipe laying work on progress 40900m pipe laid, interconnection work ongoing, 900HTC given | Koothuparamba Proj AE 2 | |
24 Apr 2023 | Pipe laying work on progress 40600m pipe laid, interconnection work ongoing, 840HTC given | Koothuparamba Proj AE 2 | |
18 Apr 2023 | Pipe laying work on progress 40300m pipe laid, interconnection work ongoing, 810HTC given | Koothuparamba Proj AE 2 | |
10 Apr 2023 | Pipe laying work on progress 40000m pipe laid, interconnection work ongoing, 810HTC given | Koothuparamba Proj AE 2 | |
05 Apr 2023 | pipe laying work on progress 39800m pipe laid, interconnection work ongoing, 800HTC given | Koothuparamba Proj AE 2 | |
30 Mar 2023 | pipe laying work on progress 39500m pipe laid, interconnection work ongoing, 800HTC given | Koothuparamba Proj AE 2 | |
16 Mar 2023 | pipe laying work on progress 39500m pipe laid,800HTC given | Koothuparamba Proj AE 2 | |
09 Mar 2023 | pipe laying work on progress 39000m pipe laid,780HTC given | Koothuparamba Proj AE 2 | |
02 Mar 2023 | pipe laying work on progress 39000m pipe laid,780HTC given | Koothuparamba Proj AE 2 | |
27 Feb 2023 | Work in progress 38500 m pipe laid,750HTCs given | Koothuparamba Proj AE 2 |