JJM-Kannur District-WSS to Kottiyur,Kelakam and Kanichar Panchayaths-Laying Distribution system from WTP and Providing FHTCs -Zone I
Project |
JJM-Kannur District-WSS to Kottiyur,Kelakam and Kanichar Panchayaths-Laying Distribution system from WTP and Providing FHTCs -Zone I |
Project Code |
KNRJJM09218490 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Laying Distribution line from Ongoing NABARD aided project and providing 4145 FHTC .total distribution line proposed in this project is 78127 m for main line and 11820 m for laying rider line and parellel line for avoiding road crossing. |
Status |
On-going |
District |
Kannur |
Executing Office |
Kannur Project Dn |
AS Amount (Rs) |
1284500000
|
AS Number |
G.O.(Rt)No.489/2021/WRD |
TS Amount (Rs) |
221500000 |
TS Number |
16894/2021-2022 |
Total Bill Submitted (Rs) |
20226528 |
Total Bill Paid (Rs) |
20226528 |
Population Benefitted |
17000 |
Capacity in MLD |
11.00 |
Actual Project Completion Date |
27 Dec 2022 |
Coverage |
Kottiyur,Kelakam and Kanichar Panchayaths Part for catering 17000 population by providing 4145 FHTC. |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
JJM-Kannur District-WSS to Kottiyur,Kelakam and Kanichar Panchayaths-Laying Distribution system from WTP and Providing FHTCs -Zone I |
Koothuparamba Project Sn No2 |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
16 May 2024 |
83613 m pipe laid and 1800 HTC given |
Koothuparamba Proj AE 2 |
|
09 May 2024 |
83005 m pipe laid and 1800 HTC given |
Koothuparamba Proj AE 2 |
|
06 May 2024 |
82812 m pipe laid and 1800 HTC given |
Koothuparamba Proj AE 2 |
|
02 May 2024 |
82550 m pipe laid and 1800 HTC given |
Koothuparamba Proj AE 2 |
|
30 Apr 2024 |
82345 m pipe laid and 1800 HTC given |
Koothuparamba Proj AE 2 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
25/04/2022 |
Scheduled date of Completion of the Project |
31 Oct 2022 |
Expected date of Completion |
31/10/2022 |
Processing Dates
AS Date |
18 Sep 2021 |
TS Date |
02 Jan 2022 |