Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
13 Sep 2023 | 53327 m pipe laid, 1200 HTC | Koothuparamba Proj AE 2 | |
05 Sep 2023 | 52806 m pipe, 1180 HTC | Koothuparamba Proj AE 2 | |
24 Aug 2023 | 52605 Pipe laid,1170 HTC | Koothuparamba Proj AE 2 | |
16 Aug 2023 | 52378 m pipe laid 1170 HTC given | Koothuparamba Proj AE 2 | |
10 Aug 2023 | Pipe laying work on progress 52000m pipe laid, interconnection work ongoing, 1160HTC given,Due to heavy rain work is slow in progress | Koothuparamba Proj AE 2 | |
03 Aug 2023 | Pipe laying work on progress 51000m pipe laid, interconnection work ongoing, 1140HTC given,Due to heavy rain work is slow in progress | Koothuparamba Proj AE 2 | |
26 Jul 2023 | Pipe laying work on progress 50000m pipe laid, interconnection work ongoing, 1110HTC given,Due to heavy rain work is slow in progress | Koothuparamba Proj AE 2 | |
19 Jul 2023 | Pipe laying work on progress 50000m pipe laid, interconnection work ongoing, 1100HTC given | Koothuparamba Proj AE 2 | |
06 Jul 2023 | Pipe laying work on progress 44800m pipe laid, interconnection work ongoing, 1000HTC given | Koothuparamba Proj AE 2 | |
30 Jun 2023 | Pipe laying work on progress 44500m pipe laid, interconnection work ongoing, 1000HTC given | Koothuparamba Proj AE 2 |