Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
30 Sep 2022 | work order issued. Agreement executed. Joint inspection conducted with KRFB officials regarding cutting permission and PVC pipe supplyed and 44500 m pipe line laid | Koothuparamba Proj AE 2 | |
20 Sep 2022 | work order issued. Agreement executed. Joint inspection conducted with KRFB officials regarding cutting permission and PVC pipe supplyed and 2000 m pipe line laid | Koothuparamba Proj AE 2 | |
12 Sep 2022 | work order issued. Agreement executed. Joint inspection conducted with KRFB officials regarding cutting permission and PVC pipe supplyed and 1000 m pipe line laid | Koothuparamba Proj AE 2 | |
05 Sep 2022 | work order issued. Agreement executed. Joint inspection conducted with KRFB officials regarding cutting permission and 50% pipe supplied , 200 m pipe laid-1 st part bill submiitted | Koothuparamba Proj AE 2 | |
01 Sep 2022 | work order issued. Agreement executed. Joint inspection conducted with KRFB officials regarding cutting permission and 50% pipe supplied , 100 m pipe laid-1 st part bill submiitted. | Koothuparamba Proj AE 2 | |
25 Aug 2022 | work order issued. Agreement executed. Joint inspection conducted with KRFB officials regarding cutting permission and 50% pipe supplyed , 100 m pipe laid | Koothuparamba Proj AE 2 | |
05 Aug 2022 | work order issued. Agreement executed. Joint inspection conducted with KRFB officials regarding cutting permission and pipe supplying started | Koothuparamba Proj AE 2 | |
29 Jul 2022 | work order issued. Agreement executed. Joint inspection conducted with KRFB officials regarding cutting permission and pipe supplying started | Koothuparamba Proj AE 2 | |
30 Jun 2022 | work order issued,Agreement executed ,Joint inspection conducted with KRFB officials regarding cutting permission. | Koothuparamba Proj AE 2 | |
24 Jun 2022 | work order issued.Agreement executed.Joint inspection conducted with KRFB officials regarding cutting permission. | Koothuparamba Proj AE 2 |