Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
01 Jan 2024 | 58000m pipe laid and 1500 htc given | Koothuparamba Proj AE 2 | |
11 Dec 2023 | 57250m pipe laid and 1428 htc given | Koothuparamba Proj AE 2 | |
06 Dec 2023 | 57250m pipe laid and 1420 htc given | Koothuparamba Proj AE 2 | |
28 Nov 2023 | 57000m pipe laid and 1400 htc given | Koothuparamba Proj AE 2 | |
17 Nov 2023 | 56000m pipe laid and 1370 htc given | Koothuparamba Proj AE 2 | |
10 Nov 2023 | 55000m pipe laid and 1345 htc given | Koothuparamba Proj AE 2 | |
02 Nov 2023 | 55000 m pipe laid, 1300 HTC | Koothuparamba Proj AE 2 | |
18 Oct 2023 | 54500 m pipe laid, 1250 HTC | Koothuparamba Proj AE 2 | |
11 Oct 2023 | 54200 m pipe laid, 1250 HTC | Koothuparamba Proj AE 2 | |
05 Oct 2023 | 54000 m pipe laid, 1250 HTC | Koothuparamba Proj AE 2 |