Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
17 Dec 2022 | Work in progress 31000 m pipe laid, 472 HTCs given View all updates | Koothuparamba Proj AE 2 | |
14 Dec 2022 | Work in progress 30800m pipe laid, 458 HTCs given View all updates | Koothuparamba Proj AE 2 | |
12 Dec 2022 | Work in progress 30000m pipe laid, 420 HTCs given | Koothuparamba Proj AE 2 | |
30 Nov 2022 | Work in progress 25000m pipe laid, 300 HTCs given View all updates | Koothuparamba Proj AE 2 | |
24 Nov 2022 | Work in progress 24000m pipe laid, 275 HTCs given View all updates | Koothuparamba Proj AE 2 | |
19 Nov 2022 | Work in progress 22000 m pipe laid, 275 HTCs given | Koothuparamba Proj AE 2 | |
17 Nov 2022 | Work in progress 21400 m pipe laid, 240 HTCs given | Koothuparamba Proj AE 2 | |
14 Nov 2022 | Work in progress 20800 m pipe laid .215nos HTCs given. | Koothuparamba Proj AE 2 | |
11 Nov 2022 | Work in progress 19915 m pipe laid (160 mm pvc 1601 m , 140 mm pvc 1593 m, 110 mm pvc 2588 m , 90 mm pvc 7500 m , 75 mm pvc 1218 m, 63 mm pvc 1467 m and 50 mm pvc 2174 m). 200 HTCs given. | Koothuparamba Proj AE 2 | |
10 Nov 2022 | 160 mm pvc 1601 m , 140 mm pvc 1593 m, 110 mm pvc 2588 m , 90 mm pvc 7500 m , 75 mm pvc 1218 m, 63 mm pvc 1467 m and 50 mm pvc 2174 m laid total 19915 m pipe laid | Koothuparamba Proj AE 2 |