Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
04 Nov 2022 160 mm pvc 1601 m , 140 mm pvc 1593 m, 110 mm pvc 2588 m , 90 mm pvc 6500 m , 75 mm pvc 1218 m, 63 mm pvc 1467 m and 50 mm pvc 1718 m laid total 16685 m pipe laid and 650 nos HTCs given Koothuparamba Proj AE 2
04 Nov 2022 160 mm pvc 1601 m , 140 mm pvc 1593 m, 110 mm pvc 2588 m , 90 mm pvc 6500 m , 75 mm pvc 1218 m, 63 mm pvc 1467 m and 50 mm pvc 1718 m laid total 16685 m pipe laid Koothuparamba Proj AE 2
02 Nov 2022 Pvc pipe supplied and 16000 m laid and 600 no's HTC GIVEN. First and part bill submitted Koothuparamba Proj AE 2
27 Oct 2022 Pvc pipe supplied and 15000 m laid and 550 nos HTC GIVEN. First and part bill submitted Koothuparamba Proj AE 2
24 Oct 2022 Pvc pipe supplied and 14500 m laid and 550 nos HTC GIVEN. First and part bill submitted Koothuparamba Proj AE 2
21 Oct 2022 Pvc pipe supplied and 14000 m laid and 500 nos HTC GIVEN. First and part bill submitted Koothuparamba Proj AE 2
17 Oct 2022 Pvc pipe supplied and 12500 m laid. First and part bill submitted Koothuparamba Proj AE 2
14 Oct 2022 Pvc pipe supplied and 11500 m laid. First and part bill submitted Koothuparamba Proj AE 2
12 Oct 2022 Pvc pipe supplied and 11000 m laid. First and part bill submitted Koothuparamba Proj AE 2
03 Oct 2022 work order issued. Agreement executed. Joint inspection conducted with KRFB officials regarding cutting permission and PVC pipe supplyed and 6000 m pipe line laid Koothuparamba Proj AE 2