Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
27 Jan 2022 | FHTC Geotagged-2446no.s (.today's geotagged connections-0-nos) FHTC -Total-2451nos.( today's physical connections-0nos)-Total pipe laid -1054 mtr | Kollam Project Dn AE | |
26 Jan 2022 | FHTC Geotagged-2446no.s (.today's geotagged connections-0-nos) FHTC -Total-2451nos.( today's physical connections-0nos) | Kollam Project Dn AE | |
25 Jan 2022 | FHTC Geotagged-2419no.s (.today's geotagged connections-0-nos) FHTC -Total-2429nos.( today's physical connections-01nos) | Kollam Project Dn AE | |
19 Jan 2022 | FHTC Geotagged-2419no.s (.today's geotagged connections-0-nos) FHTC -Total-2428nos.( today's physical connections-07nos) | Kollam Project Dn AE | |
18 Jan 2022 | FHTC Geotagged-2419no.s (.today's geotagged connections-14-nos) FHTC -Total-2421nos.( today's physical connections-06nos) | Kollam Project Dn AE | |
13 Jan 2022 | FHTC Geotagged-2378no.s (.today's geotagged connections-11-nos) FHTC -Total-2399nos.( today's physical connections-17nos) | Kollam Project Dn AE | |
11 Jan 2022 | FHTC Geotagged-2360no.s (.today's geotagged connections-12-nos) FHTC -Total-2382nos.( today's physical connections-03nos) | Kollam Project Dn AE | |
10 Jan 2022 | FHTC Geotagged-2348no.s (.today's geotagged connections-15-nos) FHTC -Total-2379 nos.( today's physical connections-08nos) | Kollam Project Dn AE | |
08 Jan 2022 | FHTC Geotagged-2333no.s (.today's geotagged connections-0-nos) FHTC -Total-2371 nos.( today's physical connections-0nos) | Kollam Project Dn AE | |
07 Jan 2022 | FHTC Geotagged-2333no.s (.today's geotagged connections-05-nos) FHTC -Total-2371 nos.( today's physical connections-04 nos) | Kollam Project Dn AE |