Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
09 Dec 2021 | FHTC Geotagged-2136no.s (.today's geotagged connections-05nos) FHTC -Total-2159nos.( today's physical connections-25nos) | Kollam Project Dn AE | |
07 Dec 2021 | FHTC Geotagged-2131no.s (.today's geotagged connections-14nos) FHTC -Total-2134nos.( today's physical connections-05nos) | Kollam Project Dn AE | |
06 Dec 2021 | FHTC Geotagged-2117no.s (.today's geotagged connections-02nos) FHTC -Total-2129nos.( today's physical connections-07nos) | Kollam Project Dn AE | |
04 Dec 2021 | FHTC Geotagged-2115no.s (.today's geotagged connections-18nos) FHTC -Total-2122nos.( today's physical connections-06nos) | Kollam Project Dn AE | |
03 Dec 2021 | FHTC Geotagged-2097no.s (.today's geotagged connections-18nos) FHTC -Total-2116nos.( today's physical connections-08nos) | Kollam Project Dn AE | |
02 Dec 2021 | FHTC Geotagged-2079no.s (.today's geotagged connections-13nos) FHTC -Total-2108nos.( today's physical connections-32nos) | Kollam Project Dn AE | |
30 Nov 2021 | FHTC Geotagged-2066no.s (.today's geotagged connections-03nos) FHTC -Total-2076nos.( today's physical connections-08Nos).work delayed due to heavy rain | Kollam Project Dn AE | |
29 Nov 2021 | FHTC Geotagged-2063no.s (.today's geotagged connections-21nos) FHTC -Total-2068nos.( today's physical connections-16Nos) | Kollam Project Dn AE | |
27 Nov 2021 | FHTC Geotagged-2042no.s (.today's geotagged connections-05nos) FHTC -Total-2052nos.( today's physical connections-05Nos) | Kollam Project Dn AE | |
27 Nov 2021 | FHTC Geotagged-2037no.s (.today's geotagged connections-18nos) FHTC -Total-2047nos.( today's physical connections-14Nos) | Kollam Project Dn AE |