Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
19 Jun 2023 | 83 FHTC long pending in pattazhy kunnicodu KRFB road. Application submitted through RoW portal rejected by KRFB since the road is under DLP. For obtaining sanction application re submitted to KRFB and this application also rejected. Hence contractor requested to pre close the work and request granted by SE, PH Circle Kollam | Kollam Project Dn EE | |
11 Apr 2023 | FHTC Geotagged-2855 nos., Package 2 - Pipe laying work completed | Kollam Project Dn EE | |
02 Apr 2023 | Package 1- FHTC Geotagged-2855, Package 2 - Pipe laying work completed | Kollam Project Dn AE | |
25 Mar 2023 | Package 1- FHTC Geotagged-2850, Package 2 - Pipe laying work completed | Kollam Project Dn EE | |
07 Jan 2023 | Package 1- FHTC Geotagged-2759, GI pipe laying work progressing - 2451.9 m completed., Package 2 - Pipe laying work progressing - 65% completed | Kollam Project Dn AE | |
31 Dec 2022 | Package 1- FHTC Geotagged-2759, GI pipe laying work progressing - 2451.9 m completed., Package 2 - Pipe laying work progressing - 3455 m completed | Kollam Project Dn AE | |
30 Dec 2022 | Package 1- FHTC Geotagged-2759, GI pipe laying work progressing - 2451.9 m completed., Package 2 - Pipe laying work progressing | Kollam Project Dn AE | |
07 Dec 2022 | Package 1-FHTC Geotagged-2747 nos, FHTC -Total-2747 nos, Package 2 - Pipe laying work progressing | Kollam Project Dn AE | |
05 Dec 2022 | Package 1-FHTC Geotagged-2747 nos, FHTC -Total-2747 nos, Package 2 - Pipe laying work progressing | Kollam Project Dn AE | |
30 Nov 2022 | Package 1-FHTC Geotagged-2747 nos, FHTC -Total-2747 nos, Package 2 - Pipe laying work progressing. | Kollam Project Dn AE |