Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
19 Jun 2023 83 FHTC long pending in pattazhy kunnicodu KRFB road. Application submitted through RoW portal rejected by KRFB since the road is under DLP. For obtaining sanction application re submitted to KRFB and this application also rejected. Hence contractor requested to pre close the work and request granted by SE, PH Circle Kollam Kollam Project Dn EE
11 Apr 2023 FHTC Geotagged-2855 nos., Package 2 - Pipe laying work completed Kollam Project Dn EE
02 Apr 2023 Package 1- FHTC Geotagged-2855, Package 2 - Pipe laying work completed Kollam Project Dn AE
25 Mar 2023 Package 1- FHTC Geotagged-2850, Package 2 - Pipe laying work completed Kollam Project Dn EE
07 Jan 2023 Package 1- FHTC Geotagged-2759, GI pipe laying work progressing - 2451.9 m completed., Package 2 - Pipe laying work progressing - 65% completed Kollam Project Dn AE
31 Dec 2022 Package 1- FHTC Geotagged-2759, GI pipe laying work progressing - 2451.9 m completed., Package 2 - Pipe laying work progressing - 3455 m completed Kollam Project Dn AE
30 Dec 2022 Package 1- FHTC Geotagged-2759, GI pipe laying work progressing - 2451.9 m completed., Package 2 - Pipe laying work progressing Kollam Project Dn AE
07 Dec 2022 Package 1-FHTC Geotagged-2747 nos, FHTC -Total-2747 nos, Package 2 - Pipe laying work progressing Kollam Project Dn AE
05 Dec 2022 Package 1-FHTC Geotagged-2747 nos, FHTC -Total-2747 nos, Package 2 - Pipe laying work progressing Kollam Project Dn AE
30 Nov 2022 Package 1-FHTC Geotagged-2747 nos, FHTC -Total-2747 nos, Package 2 - Pipe laying work progressing. Kollam Project Dn AE