Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
15 Mar 2022 | FHTC Geotagged-2531 no.s (today's geotagged connections-0-nos) FHTC -Total-2532nos.( today's physical connections-1 nos) total pipe laid - 1700.2 mtr | Kollam Project Dn AE | |
14 Mar 2022 | FHTC Geotagged-2531 no.s (today's geotagged connections-0-nos) FHTC -Total-2531nos.( today's physical connections-0 nos) total pipe laid - 1700.2 mtr | Kollam Project Dn AE | |
12 Mar 2022 | FHTC Geotagged-2531 no.s (today's geotagged connections-6-nos) FHTC -Total-2531nos.( today's physical connections-0 nos) total pipe laid - 1700.2 mtr | Kollam Project Dn AE | |
11 Mar 2022 | FHTC Geotagged-2525 no.s (today's geotagged connections-0-nos) FHTC -Total-2531nos.( today's physical connections-0 nos) total pipe laid - 1700.2 mtr | Kollam Project Dn AE | |
10 Mar 2022 | FHTC Geotagged-2525 no.s (today's geotagged connections-0-nos) FHTC -Total-2531nos.( today's physical connections-6 nos) total pipe laid - 1700.2 mtr | Kollam Project Dn AE | |
09 Mar 2022 | FHTC Geotagged-2525 no.s (today's geotagged connections-2-nos) FHTC -Total-2525nos.( today's physical connections-0 nos) total pipe laid - 1700.2 mtr | Kollam Project Dn AE | |
08 Mar 2022 | FHTC Geotagged-2523 no.s (today's geotagged connections-0-nos) FHTC -Total-2525nos.( today's physical connections-2nos) total pipe laid - 1700.2 mtr | Kollam Project Dn AE | |
07 Mar 2022 | FHTC Geotagged-2523 no.s (today's geotagged connections-0-nos) FHTC -Total-2523nos.( today's physical connections-0nos) total pipe laid - 1700.2 mtr | Kollam Project Dn AE | |
05 Mar 2022 | FHTC Geotagged-2523 no.s (today's geotagged connections-8-nos) FHTC -Total-2523nos.( today's physical connections-3nos) total pipe laid - 1700.2 mtr | Kollam Project Dn AE | |
04 Mar 2022 | FHTC Geotagged-2515 no.s (today's geotagged connections-1-nos) FHTC -Total-2520nos.( today's physical connections-4nos) total pipe laid - 1700.2 mtr | Kollam Project Dn AE |