Jal Jeevan Mission - Providing Functional Household Tap Connections at Pattazhy Panchayath in Kollam District.

Project Jal Jeevan Mission - Providing Functional Household Tap Connections at Pattazhy Panchayath in Kollam District.
Project Code KLMJJM08203111
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission - Providing Functional Household Tap Connections at Pattazhy Panchayath in Kollam District.
Status On-going
District Kollam
Executing Office Kollam Project Dn
AS Amount (Rs) 34793000
AS Number GO(Rt)No:541/2020/WRD
TS Amount (Rs) 27760000
TS Number TS/2020-2021/2020/16264
Total Bill Submitted (Rs) 21176026
Total Bill Paid (Rs) 17829157
Population Benefitted 13000
Capacity in MLD 0.70
Actual Project Completion Date Date is not specified
Coverage pattazhi panchayath
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Jal Jeevan Mission - Providing Functional Household Tap Connections at Pattazhy Panchayath in Kollam District. Kollam Project Dn
2 JJM work-Pattazhy phase 2-Extension for last mile connectivity Kollam Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
19 Jun 2023 83 FHTC long pending in pattazhy kunnicodu KRFB road. Application submitted through RoW portal rejected by KRFB since the road is under DLP. For obtaining sanction application re submitted to KRFB and this application also rejected. Hence contractor requested to pre close the work and request granted by SE, PH Circle Kollam Kollam Project Dn EE
11 Apr 2023 FHTC Geotagged-2855 nos., Package 2 - Pipe laying work completed Kollam Project Dn EE
02 Apr 2023 Package 1- FHTC Geotagged-2855, Package 2 - Pipe laying work completed Kollam Project Dn AE
25 Mar 2023 Package 1- FHTC Geotagged-2850, Package 2 - Pipe laying work completed Kollam Project Dn EE
07 Jan 2023 Package 1- FHTC Geotagged-2759, GI pipe laying work progressing - 2451.9 m completed., Package 2 - Pipe laying work progressing - 65% completed Kollam Project Dn AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 09/07/2021
Scheduled date of Completion of the Project 23 Jun 2022
Expected date of Completion 31/10/2022

Processing Dates

AS Date 25 Aug 2020
TS Date 27 Aug 2020

Other details

Project Officers View