Jal Jeevan Mission - Providing Functional Household Tap Connections at Pattazhy Panchayath in Kollam District.
Project |
Jal Jeevan Mission - Providing Functional Household Tap Connections at Pattazhy Panchayath in Kollam District. |
Project Code |
KLMJJM08203111 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Jal Jeevan Mission - Providing Functional Household Tap Connections at Pattazhy Panchayath in Kollam District. |
Status |
On-going |
District |
Kollam |
Executing Office |
Kollam Project Dn |
AS Amount (Rs) |
34793000
|
AS Number |
GO(Rt)No:541/2020/WRD |
TS Amount (Rs) |
27760000 |
TS Number |
TS/2020-2021/2020/16264 |
Total Bill Submitted (Rs) |
21176026 |
Total Bill Paid (Rs) |
17829157 |
Population Benefitted |
13000 |
Capacity in MLD |
0.70 |
Actual Project Completion Date |
Date is not specified |
Coverage |
pattazhi panchayath |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission - Providing Functional Household Tap Connections at Pattazhy Panchayath in Kollam District. |
Kollam Project Dn |
|
2 |
JJM work-Pattazhy phase 2-Extension for last mile connectivity |
Kollam Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
19 Jun 2023 |
83 FHTC long pending in pattazhy kunnicodu KRFB road. Application submitted through RoW portal rejected by KRFB since the road is under DLP. For obtaining sanction application re submitted to KRFB and this application also rejected. Hence contractor requested to pre close the work and request granted by SE, PH Circle Kollam |
Kollam Project Dn EE |
|
11 Apr 2023 |
FHTC Geotagged-2855 nos., Package 2 - Pipe laying work completed |
Kollam Project Dn EE |
|
02 Apr 2023 |
Package 1- FHTC Geotagged-2855, Package 2 - Pipe laying work completed |
Kollam Project Dn AE |
|
25 Mar 2023 |
Package 1- FHTC Geotagged-2850, Package 2 - Pipe laying work completed |
Kollam Project Dn EE |
|
07 Jan 2023 |
Package 1- FHTC Geotagged-2759, GI pipe laying work progressing - 2451.9 m completed., Package 2 - Pipe laying work progressing - 65% completed |
Kollam Project Dn AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
09/07/2021 |
Scheduled date of Completion of the Project |
23 Jun 2022 |
Expected date of Completion |
31/10/2022 |
Processing Dates
AS Date |
25 Aug 2020 |
TS Date |
27 Aug 2020 |