Status Date Overall Project Status Project Officer Contact
25 Nov 2021 FHTC Geotagged-2019no.s (.today's geotagged connections-04nos) FHTC -Total-2033nos.( today's physical connections-10Nos) Kollam Project Dn AE
24 Nov 2021 FHTC Geotagged-2015no.s (.today's geotagged connections-15nos) FHTC -Total-2025nos.( today's physical connections-15Nos) Kollam Project Dn AE
23 Nov 2021 FHTC Geotagged-2000no.s (.today's geotagged connections-23nos) FHTC -Total-2010nos.( today's physical connections-19Nos) Kollam Project Dn AE
22 Nov 2021 FHTC Geotagged-1977no.s (.today's geotagged connections-04nos) FHTC -Total-1991nos.( today's physical connections-16Nos) Kollam Project Dn AE
20 Nov 2021 FHTC Geotagged-1973no.s (.today's geotagged connections-05nos) FHTC -Total-1975nos.( today's physical connections-05Nos) Kollam Project Dn AE
19 Nov 2021 FHTC Geotagged-1968no.s (.today's geotagged connections-05nos) FHTC -Total-1968nos.( today's physical connections-05Nos).-work delayed due to heavy rain Kollam Project Dn AE
18 Nov 2021 FHTC Geotagged-1963no.s (.today's geotagged connections-19nos) FHTC -Total-1963nos.( today's physical connections-16Nos). Kollam Project Dn AE
17 Nov 2021 FHTC Geotagged-1944no.s (.today's geotagged connections-14nos) FHTC -Total-1947nos.( today's physical connections-17Nos). Kollam Project Dn AE
16 Nov 2021 FHTC Geotagged-1930no.s (.today's geotagged connections-0nos) FHTC -Total-1930nos.( today's physical connections-0Nos).-work delayed due to heavy rain Kollam Project Dn AE
15 Nov 2021 FHTC Geotagged-1930no.s (.today's geotagged connections-0nos) FHTC -Total-1930nos.( today's physical connections-0Nos).-work delayed due to heavy rain Kollam Project Dn AE