Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
08 Feb 2022 | FHTC Geotagged-2460 no.s (.today's geotagged connections-6-nos) FHTC -Total-2464nos.( today's physical connections-5nos)-Total pipe laid -1257 mtr | Kollam Project Dn AE | |
07 Feb 2022 | FHTC Geotagged-2454 no.s (.today's geotagged connections-0-nos) FHTC -Total-2459nos.( today's physical connections-0 nos)-Total pipe laid -1257 mtr | Kollam Project Dn AE | |
06 Feb 2022 | FHTC Geotagged-2454 no.s (.today's geotagged connections-0-nos) FHTC -Total-2459nos.( today's physical connections-0 nos)-Total pipe laid -1257 mtr | Kollam Project Dn AE | |
05 Feb 2022 | FHTC Geotagged-2454 no.s (.today's geotagged connections-0-nos) FHTC -Total-2459nos.( today's physical connections-0 nos)-Total pipe laid -1257 mtr | Kollam Project Dn AE | |
04 Feb 2022 | FHTC Geotagged-2454 no.s (.today's geotagged connections-8-nos) FHTC -Total-2459nos.( today's physical connections-8 nos)-Total pipe laid -1257 mtr | Kollam Project Dn AE | |
03 Feb 2022 | FHTC Geotagged-2446no.s (.today's geotagged connections-0-nos) FHTC -Total-2451nos.( today's physical connections-0 nos)-Total pipe laid -1257 mtr | Kollam Project Dn AE | |
02 Feb 2022 | FHTC Geotagged-2446no.s (.today's geotagged connections-0-nos) FHTC -Total-2451nos.( today's physical connections-0 nos)-Total pipe laid -1257 mtr | Kollam Project Dn AE | |
01 Feb 2022 | FHTC Geotagged-2446no.s (.today's geotagged connections-0-nos) FHTC -Total-2451nos.( today's physical connections-0nos)-Total pipe laid -1257 mtr | Kollam Project Dn AE | |
30 Jan 2022 | FHTC Geotagged-2446no.s (.today's geotagged connections-0-nos) FHTC -Total-2451nos.( today's physical connections-0nos)-Total pipe laid -1257 mtr | Kollam Project Dn AE | |
28 Jan 2022 | FHTC Geotagged-2446no.s (.today's geotagged connections-0-nos) FHTC -Total-2451nos.( today's physical connections-0nos)-Total pipe laid -1257 mtr | Kollam Project Dn AE |