Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
02 Mar 2023 | 175606m laying completed, 1195 connections completed, 11th and part bill submitted | Chavara AE | |
27 Feb 2023 | 175606m laying completed, 1191 connections completed, 11th and part bill submitted | Chavara AE | |
24 Feb 2023 | 175606m laying completed, 1191 connections completed, 11th and part bill submitted | Chavara AE | |
21 Feb 2023 | 175606m laying completed, 1191 connections completed, 11th and part bill submitted | Chavara AE | |
17 Feb 2023 | 175606m laying completed, 1187 connections completed, 11th and part bill submitted | Chavara AE | |
17 Feb 2023 | 175606m laying completed, 1187 connections completed, 11th and part bill submitted | Chavara AE | |
14 Feb 2023 | 175606m laying completed, 1182 connections completed, 11th and part bill submitted | Chavara AE | |
10 Feb 2023 | 175606m laying completed, 1179 connections completed, 11th and part bill submitted | Chavara AE | |
08 Feb 2023 | 175606m laying completed, 1175 connections completed, 10th and part bill submitted | Chavara AE | |
06 Feb 2023 | 17396m laying completed, 1175 connections completed, 10th and part bill submitted | Chavara AE |