Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
02 Feb 2023 | 17396m laying completed, 1175 connections completed, 10th and part bill submitted | Chavara AE | |
30 Jan 2023 | 17396m laying completed, 1172 connections completed, 10th and part bill submitted | Chavara AE | |
27 Jan 2023 | 17396m laying completed, 1168 connections completed, 10th and part bill submitted | Chavara AE | |
24 Jan 2023 | 17396m laying completed, 1163 connections completed, 10th and part bill submitted | Chavara AE | |
21 Jan 2023 | 17396m laying completed, 1158 connections completed, 10th and part bill submitted | Chavara AE | |
19 Jan 2023 | 17396m laying completed, 1154 connections completed, 10th and part bill submitted | Chavara AE | |
16 Jan 2023 | 17396m laying completed, 1150 connections completed, 10th and part bill submitted | Chavara AE | |
13 Jan 2023 | 17396m laying completed, 1142 connections completed, 10th and part bill submitted | Chavara AE | |
13 Jan 2023 | 17396m laying completed, 1142 connections completed, 10th and part bill submitted | Chavara AE | |
10 Jan 2023 | 17396m laying completed, 1131 connections completed, 10th and part bill submitted | Chavara AE |