Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
07 Jan 2023 | 17396m laying completed, 1128 connections completed, 10th and part bill submitted | Chavara AE | |
05 Jan 2023 | 10th and part bill submitted | Chavara AE | |
03 Jan 2023 | 10th and part bill submitted | Chavara AE | |
28 Dec 2022 | Out of 2388 connections 1104connections completed | Chavara AE | |
26 Dec 2022 | Out of 2388 connections 1104connections completed | Chavara AE | |
23 Dec 2022 | Out of 2388 connections 1104connections completed | Chavara AE | |
20 Dec 2022 | 9th and part bill submitted | Chavara AE | |
16 Dec 2022 | 9th and part bill submitted | Chavara AE | |
12 Dec 2022 | Out of 2388 connections 1068connections completed | Chavara AE | |