Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
03 Dec 2022 | Out of 2388 connections 998connections completed | Chavara AE | |
29 Nov 2022 | Out of 2388 connections 994connections completed | Chavara AE | |
24 Nov 2022 | Out of 2388 connections 956connections completed | Chavara AE | |
21 Nov 2022 | Out of 2388 connections 956connections completed | Chavara AE | |
15 Nov 2022 | Out of 2388 connections 900connections completed | Chavara AE | |
11 Nov 2022 | Out of 2388 connections 892connections completed | Chavara AE | |
07 Nov 2022 | CC VII nth and part bill submitted | Chavara AE | |
03 Nov 2022 | Out of 2388 connections 850 connections completed | Chavara AE | |
31 Oct 2022 | Out of 2388 connections 844 connections completed | Chavara AE | |
27 Oct 2022 | Out of 2388 connections 844 connections completed | Chavara AE |