Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
19 Jul 2023 | 3200m laying completed, 1348 connections completed, 13th and part bill submitted | Chavara AE | |
14 Jul 2023 | 3200m laying completed, 1348 connections completed, 13th and part bill submitted | Chavara AE | |
11 Jul 2023 | 3200m laying completed, 1344 connections completed, 13th and part bill submitted | Chavara AE | |
07 Jul 2023 | 3200m laying completed, 1339 connections completed, 13th and part bill submitted | Chavara AE | |
04 Jul 2023 | 3200m laying completed, 1339 connections completed, 13th and part bill submitted | Chavara AE | |
30 Jun 2023 | 3200m laying completed, 1337 connections completed, 13th and part bill submitted | Chavara AE | |
27 Jun 2023 | 3200m laying completed, 1337 connections completed, 13th and part bill submitted | Chavara AE | |
23 Jun 2023 | 3200m laying completed, 1337 connections completed, 13th and part bill submitted | Chavara AE | |
20 Jun 2023 | 3200m laying completed, 1337 connections completed, 13th and part bill submitted | Chavara AE | |
16 Jun 2023 | 3200m laying completed, 1298 connections completed, 13th and part bill submitted | Chavara AE |