JAL JEEVAN MISSION - Phase I (2020-22) - CWSS to Thevalakara Thekkumbhagom - Supply and Laying Distribution lines - DI, MS, PVC, GI, HDPE pipes of various size as per design provided, Providing FHTC (2388 Nos.), Construction of Tube well, Supply of Standby Submersible pump sets, Installation of Bulk Water Meters etc. in Thekkumbhagam Panchayat.

Project JAL JEEVAN MISSION - Phase I (2020-22) - CWSS to Thevalakara Thekkumbhagom - Supply and Laying Distribution lines - DI, MS, PVC, GI, HDPE pipes of various size as per design provided, Providing FHTC (2388 Nos.), Construction of Tube well, Supply of Standby Submersible pump sets, Installation of Bulk Water Meters etc. in Thekkumbhagam Panchayat.
Project Code KLMJJM082010664
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JAL JEEVAN MISSION - Phase I (2020-22) - CWSS to Thevalakara Thekkumbhagom - Supply and Laying Distribution lines - DI, MS, PVC, GI, HDPE pipes of various size as per design provided, Providing FHTC (2388 Nos.), Construction of Tube well, Supply of Standby Submersible pump sets, Installation of Bulk Water Meters etc. in Thekkumbhagam Panchayat.
Status On-going
District Kollam
Executing Office Kollam PH Dn
AS Amount (Rs) 118018000
AS Number 541/2020/WRD
TS Amount (Rs) 106000000
TS Number 13797/2021-2022
Total Bill Submitted (Rs) 26586751
Total Bill Paid (Rs) 26586751
Population Benefitted 35000
Capacity in MLD 0.36
Actual Project Completion Date 24 Mar 2023
Coverage thekkumbhagom panchayath and adjoining areas
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 JAL JEEVAN MISSION - Phase I (2020-22) - CWSS to Thevalakara Thekkumbhagom - Supply and Laying Distribution lines - DI, MS, PVC, GI, HDPE pipes of various size as per design provided, Providing FHTC (2388 Nos.), Construction of Tube well, Supply of Standby Submersible pump sets, Installation of Bulk Water Meters etc. in Thekkumbhagam Panchayat. Chavara PH Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
26 Jun 2024 43800m laying completed,1537 connections completed, 15th and part bill submitted. Chavara AE
23 Jun 2024 43800m laying completed,1537 connections completed, 15th and part bill submitted. Chavara AE
20 Jun 2024 43800m laying completed,1537 connections completed, 15th and part bill submitted. Chavara AE
17 Jun 2024 43800m laying completed,1537 connections completed, 15th and part bill submitted. Chavara AE
14 Jun 2024 43800m laying completed,1537 connections completed, 15th and part bill submitted. Chavara AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 25/03/2022
Scheduled date of Completion of the Project 24 Mar 2023
Expected date of Completion 31/05/2024

Processing Dates

AS Date 21 Aug 2020
TS Date 24 Nov 2021

Other details

Project Officers View