Overall Project Status

Status Date Overall Project Status Project Officer Contact
08 May 2023 3200m laying completed, 1279 connections completed, 12th and part bill submitted Chavara AE
04 May 2023 3200m laying completed, 1270 connections completed, 12th and part bill submitted Chavara AE
01 May 2023 3200m laying completed, 1268 connections completed, 12th and part bill submitted Chavara AE
27 Apr 2023 3200m laying completed, 1266 connections completed, 12th and part bill submitted Chavara AE
24 Apr 2023 3200m laying completed, 1266 connections completed, 12th and part bill submitted Chavara AE
19 Apr 2023 17560m laying completed, 1254 connections completed, 12th and part bill submitted Kollam PH Dn EE
17 Apr 2023 175606m laying completed, 1254 connections completed, 12th and part bill submitted Chavara AEE
13 Apr 2023 175606m laying completed, 1248 connections completed, 12th and part bill submitted Chavara AE
10 Apr 2023 175606m laying completed, 1244 connections completed, 12th and part bill submitted Chavara AE
04 Apr 2023 175606m laying completed, 1242 connections completed, 12th and part bill submitted Chavara AE