Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
27 Mar 2023 | Packages 1,2,3,4,5 are Completed, Package 6- Work is in Progress. | Cherpu AE | |
22 Mar 2023 | Packages 1,2,3,4,5 are Completed, Package 6- Work is in Progress. | Cherpu AE | |
21 Mar 2023 | Packages 1,2,3,4,5 are Completed, Package 6- Work is in Progress. | Cherpu AE | |
21 Mar 2023 | Packages 1,3,4 and 5 are completed. Package 2 work is ongoing and 72% completed. Package 6 Work Completed. | Cherpu AE | |
18 Mar 2023 | Packages 1,3,4 and 5 are completed. Package 2 work is ongoing and 72% completed. Package 6 Work Completed. | Cherpu AE | |
15 Mar 2023 | Packages 1,3,4 and 5 are completed. Package 2 work is ongoing and 72% completed. Package 6 Work Completed. | Cherpu AE | |
13 Mar 2023 | Packages 1,3,4 and 5 are completed. Package 2 work is ongoing and 72% completed. Package 6 Work Completed. | Cherpu AE | |
10 Mar 2023 | Packages 1,3,4 and 5 are completed. Package 2 work is ongoing and 72% completed. Package 6 Work Completed. | Cherpu AE | |
07 Mar 2023 | Packages 1,3,4 and 5 are completed. Package 2 work is ongoing and 71% completed. Package 6 Work Completed. | Cherpu AE | |
04 Mar 2023 | Packages 1,3,4 and 5 are completed. Package 2 work is ongoing and 71% completed. Package 6 Work Completed. | Cherpu AE |