Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
02 Mar 2023 | Packages 1,3,4 and 5 are completed. Package 2 work is ongoing and 71% completed. Package 6 Work Completed. | Cherpu AE | |
27 Feb 2023 | Packages 1,3,4 and 5 are completed. Package 2 work is ongoing and 71% completed. Package 6 Work Completed. | Cherpu AE | |
27 Feb 2023 | Packages 1,3,4 and 5 are completed. Package 2 work is ongoing and 70% completed. Package 6 Work Completed. | Cherpu AE | |
24 Feb 2023 | Packages 1,3,4 and 5 are completed. Package 2 work is ongoing and 70% completed. Package 6 Work Completed. | Cherpu AE | |
21 Feb 2023 | Packages 1,3,4 and 5 are completed. Package 2 work is ongoing and 70% completed. Package 6 Work Completed. | Cherpu AE | |
10 Feb 2023 | Packages 1,3,4 and 5 are completed. Package 2 work is ongoing and 70% completed. Package 6 Work is in Progress. | Cherpu AE | |
06 Feb 2023 | Packages 1,3,4 and 5 are completed. Package 2 work is ongoing and 70% completed. Package 6 Work Started on 01-02-2023. | Cherpu AE | |
03 Feb 2023 | Packages 1,3,4 and 5 are completed. Package 2 work is ongoing and 70% completed. Package 6 Work Started on 01-02-2023. | Cherpu AE | |
01 Feb 2023 | Packages 1,3,4 and 5 are completed. Package 2 work is ongoing and 70% completed. Package 6 Work Started on 01-02-2023. | Cherpu AE | |
30 Jan 2023 | Packages 1,3,4 and 5 are completed. Package 2 work is ongoing and 70% completed. Package 6 road-cutting sanction is not obtained. | Cherpu AE |