JJM-2020-21 - Cherpu Grama Panchayath - SPAN Urakam and adjoining villages - Leak rectification works of GL tank at Pallisserykunnu & Providing 3794 nos of service water connections .
Project |
JJM-2020-21 - Cherpu Grama Panchayath - SPAN Urakam and adjoining villages - Leak rectification works of GL tank at Pallisserykunnu & Providing 3794 nos of service water connections . |
Project Code |
TCRJJM08203896 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
JJM-2020-21 - Cherpu Grama Panchayath - SPAN Urakam and adjoining villages - Leak rectification works of GL tank at Pallisserykunnu & Providing 3794 nos of service water connections . |
Status |
On-going |
District |
Thrissur |
Executing Office |
Cherpu PH Sn |
AS Amount (Rs) |
103550000
|
AS Number |
G.O.(Rt)No. 541/2020/WRD |
TS Amount (Rs) |
73600000 |
TS Number |
TS/2020-2021/2020/13962 |
Total Bill Submitted (Rs) |
46537561 |
Total Bill Paid (Rs) |
46537561 |
Population Benefitted |
16000 |
Capacity in MLD |
18.00 |
Actual Project Completion Date |
31 Mar 2022 |
Coverage |
35% |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
JJM-2020-21-Cherpu GP.Providing FHTCs (10 Nos) in Poochunnipadam-Chathakudam road in Cherpu Grama Panchayath. |
Cherpu PH Sn |
|
2 |
JJM-2021-22 - Cherpu Grama Panchayath - Providing 3762 nos of service water connections and Extension of pipe lines at various places for full coverage of FHTC |
Cherpu PH Sn |
|
3 |
JJM - 20-21- Cherpu GP - WSS to Oorakam and adjoining villages - Providing 3794 numbers of water connections - APP 18C - Augmentable(MVS)-Leak rectification works of GL tank at Pallisserikunnu |
Cherpu PH Sn |
|
4 |
JJM- Cherpu Grama Panchayath - Providing 3762 nos of service water connections and Extension of pipe lines at various places for full coverage of FHTC-Pipe laying Balance work |
Cherpu PH Sn |
|
5 |
JJM - Cherpu Grama Panchayath-Providing service water connections and Extension of Pipelines at various places for full coverage of FHTC -BALANCE WORK |
Cherpu PH Sn |
|
6 |
JJM - Cherpu panchayath (part I ) - providing fhtc for rural househaols(1)- 32 nos |
Cherpu PH Sn |
|
7 |
JJM - Cherpu Panchayath - Replacing 300 mm AC pipe line along Poochunnipadam - Chathakudam PWD road by using 200 mm DI due to continuous leakage and PWD tarring work. |
Cherpu PH Sn |
|
8 |
JJM Cherpu Panchayath- Utility Shifting of KWA pipeline of Cherpu Grama Pt at Chevoor Kappela- Parakovil-Thiruvullakavu road of Cherpu Block |
Cherpu PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
25 Jun 2024 |
Package 1: Work split and Tendered, Package 2: Work completed, Package 3: Work completed and Final Bill Submitted, Package 4: Agreement Executed, Work Not Started, Package 5: 82% work completed. |
Cherpu AE |
|
22 Jun 2024 |
Package 1: Work split and Tendered, Package 2: Work completed, Package 3: Work completed and Final Bill Submitted, Package 4: Agreement Executed, Work Not Started, Package 5: 82% work completed. |
Cherpu AE |
|
19 Jun 2024 |
Package 1: Work split and Tendered, Package 2: Work completed, Package 3: Work completed and Final Bill Submitted, Package 4: Agreement Executed, Work Not Started, Package 5: 82% work completed. |
Cherpu AE |
|
16 Jun 2024 |
Package 1: Work split and Tendered, Package 2: Work completed, Package 3: Work completed and Final Bill Submitted, Package 4: Agreement Executed, Work Not Started, Package 5: 82% work completed. |
Cherpu AE |
|
13 Jun 2024 |
Package 1: Work split and Tendered, Package 2: Work completed, Package 3: Work completed and Final Bill Submitted, Package 4: Agreement Executed, Work Not Started, Package 5: 82% work completed. |
Cherpu AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
01/03/2021 |
Scheduled date of Completion of the Project |
20 May 2021 |
Expected date of Completion |
31/03/2024 |
Processing Dates
AS Date |
21 Aug 2020 |
TS Date |
04 Sep 2020 |