Status Date |
Overall Project Status |
Project Officer |
Contact |
03 Jun 2023 |
Package 1,2,3,4,5 are Completed, Package 6- Connection work is in Progress, Pipe laying work 98% completed. Package 7- work order issued, work not started. |
Cherpu AE |
|
02 Jun 2023 |
Package 1,2,3,4,5 are Completed, Package 6- Connection work is in Progress, Pipe laying work 98% completed. Package 7- work order issued, work not started. |
Cherpu AE |
|
01 Jun 2023 |
Package 1,2,3,4,5 are Completed, Package 6- Connection work is in Progress, Pipe laying work 98% completed. Package 7- work order issued, work not started. |
Cherpu AE |
|
29 May 2023 |
Package 1,2,3,4,5 are Completed, Package 6- Connection work is in Progress, Pipe laying work 98% completed. Package 7- work order issued, work not started. |
Cherpu AE |
|
27 May 2023 |
Package 1,2,3,4,5 are Completed, Package 6- Connection work is in Progress, Pipe laying work 98% completed. Package 7- work order issued, work not started. |
Cherpu AE |
|
23 May 2023 |
Packages 1,2,3,4,5 are Completed, Package 6- Connection work is in Progress, Total connection-3377 nos, Pipe laying work 98% completed. Package 7- work order issued, work not started. |
Cherpu AE |
|
20 May 2023 |
Packages 1,2,3,4,5 are Completed, Package 6- Connection work is in Progress, Total connection-3369 nos. Package 7- work order issued, work not started. |
Cherpu AE |
|
17 May 2023 |
Packages 1,2,3,4,5 are Completed, Package 6- Connection work is in Progress. Package 7- work order issued, work not started. |
Cherpu AE |
|
16 May 2023 |
Packages 1,2,3,4,5 are Completed, Package 6- 63mm PVC Pipeline work and Connection work is in Progress. Package 7- work order issued, work not started. |
Cherpu AE |
|
15 May 2023 |
Packages 1,2,3,4,5 are Completed, Package 6- 63mm PVC Pipeline work and Connection work is in Progress. Package 7- work order issued, work not started. |
Cherpu AE |
|