Status Date |
Overall Project Status |
Project Officer |
Contact |
12 May 2023 |
Packages 1,2,3,4,5 are Completed, Package 6- 63mm PVC Pipeline work and Connection work is in Progress. Package 7- work order issued, work not started. |
Cherpu AE |
|
11 May 2023 |
Packages 1,2,3,4,5 are Completed, Package 6- 75mm PVC Pipeline work and Connection work is in Progress. Package 7- work order issued, work not started. |
Cherpu AE |
|
10 May 2023 |
Packages 1,2,3,4,5 are Completed, Package 6- 75mm PVC Pipeline work and Connection work is in Progress. Package 7- work order issued, work not started. |
Cherpu AE |
|
09 May 2023 |
Packages 1,2,3,4,5 are Completed, Package 6- 63mm PVC Pipeline work and Connection work is in Progress. Package 7- work order issued, work not started. |
Cherpu AE |
|
05 May 2023 |
Packages 1,2,3,4,5 are Completed, Package 6- 63mm PVC Pipeline work and Connection work is in Progress. Package 7- work order issued, work not started. |
Cherpu AE |
|
04 May 2023 |
Packages 1,2,3,4,5 are Completed, Package 6- 63mm PVC Pipeline work and Connection work is in Progress. Package 7- work order issued, work not started |
Cherpu AE |
|
03 May 2023 |
Packages 1,2,3,4,5 are Completed, Package 6- 63mm PVC Pipeline work and Connection work is in Progress. Package 7- work order issued, work not started |
Cherpu AE |
|
02 May 2023 |
Packages 1,2,3,4,5 are Completed, Package 6- Pipeline work and Connection work is in Progress.Package 7- work order issued, work not started |
Cherpu AE |
|
29 Apr 2023 |
Packages 1,2,3,4,5 are Completed, Package 6- Pipeline work and Connection work is in Progress.Package 7- work order issued, work not started |
Cherpu AE |
|
28 Apr 2023 |
Packages 1,2,3,4,5 are Completed, Package 6- Pipeline work and Connection work is in Progress.Package 7- work order issued, work not started |
Cherpu AE |
|