27 Jan 2023 Packages 1,3,4 and 5 are completed. Package 2 work is ongoing and 70% completed. Package 6 road-cutting sanction is not obtained. Cherpu AE
24 Jan 2023 Packages 1,3,4 and 5 are completed. Package 2 work is ongoing and 70% completed. Package 6 road-cutting sanction is not obtained. Cherpu AE
21 Jan 2023 Packages 1,3,4 and 5 are completed. Package 2 work is ongoing and 70% completed. Package 6 road-cutting sanction is not obtained. Cherpu AE
16 Jan 2023 Packages 1,3,4 and 5 are completed. Package 2 work is ongoing and 70% completed. Package 6 road-cutting sanction is not obtained. Cherpu AE
13 Jan 2023 Packages 1,3,4 and 5 are completed. Package 2 work is ongoing and 70% completed. Package 6 road-cutting sanction is not obtained. Cherpu AE
11 Jan 2023 Packages 1,3,4 and 5 are completed. Package 2 work is ongoing and 70% completed. Package 6 road-cutting sanction is not obtained. Cherpu AE
09 Jan 2023 Packages 1,3,4 and 5 are completed. Package 2 work is ongoing and 70% completed. Package 6 road-cutting sanction is not obtained. Cherpu AE
06 Jan 2023 Packages 1,3,4 and 5 are completed. Package 2 work is ongoing and 70% completed. Package 6 road-cutting sanction is not obtained. Cherpu AE
05 Jan 2023 Packages 1,3,4 and 5 are completed. Package 2 work is ongoing and 70% completed. Package 6 road-cutting sanction is not obtained. Cherpu AE
03 Jan 2023 Packages 1,3,4 and 5 are completed. Package 2 work is ongoing and 70% completed. Package 6 road-cutting sanction is not obtained. Cherpu AE