Status Date |
Overall Project Status |
Project Officer |
Contact |
22 Jun 2023 |
Package 1,2,3,4,6 are Completed, Package 5- Connection work is in Progress. Package 7- Pipe Laying Work is in progress at Illakkal Dam road. |
Cherpu AE |
|
21 Jun 2023 |
Package 1,2,3,4,6 are Completed, Package 5- Connection work is in Progress, Pipe laying work 98% completed, Package 7- Pipe Laying Work is in progress. |
Cherpu AE |
|
20 Jun 2023 |
Package 1,2,3,4,6 are Completed, Package 5- Connection work is in Progress, Pipe laying work 98% completed, Package 7- Pipe Laying Work is in progress. |
Cherpu AE |
|
19 Jun 2023 |
Package 1,2,3,4,6 are Completed, Package 5- Connection work is in Progress, Pipe laying work 98% completed, connection work is in Progress. Package 7- Pipe Laying Work is in progress. |
Cherpu AE |
|
18 Jun 2023 |
Package 1,2,3,4,5 are Completed, Package 6- Connection work is in Progress, Pipe laying work 98% completed. Package 7- Pipe Laying Work is in progress. |
Cherpu AE |
|
14 Jun 2023 |
Package 1,2,3,4,5 are Completed, Package 6- Connection work is in Progress, Pipe laying work 98% completed. Package 7- Work is in progress. |
Cherpu AE |
|
11 Jun 2023 |
Package 1,2,3,4,5 are Completed, Package 6- Connection work is in Progress, Pipe laying work 98% completed. Package 7- Work Just Started |
Cherpu AE |
|
09 Jun 2023 |
Package 1,2,3,4,5 are Completed, Package 6- Connection work is in Progress, Pipe laying work 98% completed. Package 7- Work Just Started |
Cherpu AE |
|
07 Jun 2023 |
Package 1,2,3,4,5 are Completed, Package 6- Connection work is in Progress, Pipe laying work 98% completed. Package 7- Work Just Started. |
Cherpu AE |
|
06 Jun 2023 |
Package 1,2,3,4,5 are Completed, Package 6- Connection work is in Progress, Pipe laying work 98% completed. Package 7- work order issued, work not started. |
Cherpu AE |
|