Status Date |
Overall Project Status |
Project Officer |
Contact |
12 Oct 2023 |
Package 1,2,3,4,6 are Completed, Package 6- 95% work is Completed, and Package 7- 90% work completed. |
Cherpu AE |
|
09 Oct 2023 |
Package 1,2,3,4,6 are Completed, Package 6- 90% work is Completed, and Package 7- 90% work completed. |
Cherpu AE |
|
05 Oct 2023 |
Package 1,2,3,4,6 are Completed, Package 6- 90% work is Completed, and Package 7- 90% work is in Progress. |
Cherpu AE |
|
03 Oct 2023 |
Package 1,2,3,4,6 are Completed, Package 6- 90% work is Completed, and Package 7- 87% work is in Progress. |
Cherpu AE |
|
27 Sep 2023 |
Package 1,2,3,4,6 are Completed, Package 6- 90% work is Completed, and Package 7- 87% work is in Progress. |
Cherpu AE |
|
23 Sep 2023 |
Package 1,2,3,4,6 are Completed, Package 6- 90% work is Completed, and Package 7- 87% work is in Progress. |
Cherpu AE |
|
21 Sep 2023 |
Package 1,2,3,4,6 are Completed, Package 6- 90% work is Completed, and Package 7- 86% work is in Progress. |
Cherpu AE |
|
19 Sep 2023 |
Package 1,2,3,4,6 are Completed, Package 6- 90% work is Completed, and Package 7- 86% work is in Progress. |
Cherpu AE |
|
16 Sep 2023 |
Package 1,2,3,4,6 are Completed, Package 6- 90% work is Completed, and Package 7- 86% work is in Progress. |
Cherpu AE |
|
14 Sep 2023 |
Package 1,2,3,4,6 are Completed, Package 6- 90% work is Completed, and Package 7- 86% work is in Progress. |
Cherpu AE |
|