Overall Project Status

Status Date Overall Project Status Project Officer Contact
28 Jun 2024 PKG 1(Phase 1)-100 %Work completed. (Phase 2)Work1-30% Work started on 20/2/24 ongoing, Work ongoing.-Laying work completed .Restoration work pending. Work 2 -50% Work started on 1/2/24. Work ongoing pipe laying progress., Work 3- Work order issued on 26.10.2023. Agreement executed on 7.11.2023. Not started , Work 4- pipe laying 90% completed 63 FTHCs given ongoing, Work 5 -2329 M laid out of 4637m 50% Completed . pipe line work in progress. 3rd and part bill scrutiny at division. Final bill under preparation, Work 6-100% completed . Kunnamkulam PH Sn - AE
28 Jun 2024 PKG 1(Phase 1)-100 %Work completed. (Phase 2)Work1-30% Work started on 20/2/24 ongoing, Work ongoing.-Laying work completed .Restoration work pending. Work 2 -50% Work started on 1/2/24. Work ongoing pipe laying progress., Work 3- Work order issued on 26.10.2023. Agreement executed on 7.11.2023. Not started , Work 4- pipe laying 80% completed 63 FTHCs given ongoing, Work 5 -2329 M laid out of 4637m . pipe line work in progress. 3rd and part bill scrutiny at division. Final bill under preparation, Work 6-100% completed . Kunnamkulam PH Sn - AE
28 Jun 2024 PKG 1(Phase 1)-100 %Work completed. (Phase 2)Work1-30% Work started on 20/2/24 ongoing, Work ongoing.-Laying work completed .Restoration work pending. Work 2 -50% Work started on 1/2/24. Work ongoing pipe laying progress., Work 3- Work order issued on 26.10.2023. Agreement executed on 7.11.2023. Not started , Work 4- pipe laying 80% completed 63 FTHCs given ongoing, Work 5 -2329 M laid out of 4637m . pipe line work in progress. 3rd and part bill scrutiny at division. Final bill under preparation, Work 6-100% completed . Thrissur PH Dn EE
27 Jun 2024 PKG 1(Phase 1)-100 %Work completed. (Phase 2)Work1-15% Work started on 20/2/24 ongoing, Work 2 -50% Work started on 1/2/24 ongoing, Work 3-not started , Work 4- pipe laying 80% completed 63 FTHCs given ongoing, Work 5 -25% Work order issued on 26/10/23 agreement executed on 7/11/23 ongoing, Work 6-100% completed . Kunnamkulam PH Sn - AE
25 Jun 2024 PKG 1(Phase 1)-100 %Work completed. (Phase 2)Work1-15% Work started on 20/2/24 ongoing, Work 2 -50% Work started on 1/2/24 ongoing, Work 3-not started , Work 4- pipe laying 80% completed 63 FTHCs given ongoing, Work 5 -25% Work order issued on 26/10/23 agreement executed on 7/11/23 ongoing, Work 6-100% completed . Kunnamkulam PH Sn - AE
24 Jun 2024 PKG 1(Phase 1)-100 %Work completed. (Phase 2)Work1-15% Work started on 20/2/24 ongoing, Work 2 -50% Work started on 1/2/24 ongoing, Work 3-not started , Work 4- pipe laying 80% completed 63 FTHCs given ongoing, Work 5 -25% Work order issued on 26/10/23 agreement executed on 7/11/23 ongoing, Work 6-100% completed . Kunnamkulam PH Sn - AE
22 Jun 2024 PKG 1(Phase 1)-100 %Work completed. (Phase 2)Work1-15% Work started on 20/2/24 ongoing, Work 2 -50% Work started on 1/2/24 ongoing, Work 3-not started , Work 4- pipe laying 80% completed 63 FTHCs given ongoing, Work 5 -25% Work order issued on 26/10/23 agreement executed on 7/11/23 ongoing, Work 6-100% completed . Kunnamkulam PH Sn - AE
21 Jun 2024 PKG 1(Phase 1)-100 %Work completed. (Phase 2)Work1-15% Work started on 20/2/24 ongoing, Work 2 -50% Work started on 1/2/24 ongoing, Work 3-not started , Work 4- pipe laying 80% completed 63 FTHCs given ongoing, Work 5 -25% Work order issued on 26/10/23 agreement executed on 7/11/23 ongoing, Work 6-100% completed . Thrissur PH Dn EE
20 Jun 2024 PKG 1(Phase 1)-100 %Work completed. (Phase 2)Work1-15% Work started on 20/2/24 ongoing, Work 2 -50% Work started on 1/2/24 ongoing, Work 3-not started , Work 4- pipe laying 80% completed 63 FTHCs given ongoing, Work 5 -25% Work order issued on 26/10/23 agreement executed on 7/11/23 ongoing, Work 6-100% completed . Kunnamkulam PH Sn - AE
19 Jun 2024 PKG 1(Phase 1)-100 %Work completed. (Phase 2)Work1-15% Work started on 20/2/24 ongoing, Work 2 -50% Work started on 1/2/24 ongoing, Work 3-not started , Work 4- pipe laying 80% completed 63 FTHCs given ongoing, Work 5 -25% Work order issued on 26/10/23 agreement executed on 7/11/23 ongoing, Work 6-100% completed . Kunnamkulam PH Sn - AE