Status Date |
Overall Project Status |
Project Officer |
Contact |
23 May 2024 |
PKG 1(Phase 1)-100 %Work completed. (Phase 2)Work1-15% Work started on 20/2/24 ongoing, Work 2 -50% Work started on 1/2/24 ongoing, Work 3-not started , Work 4- 60% pipe laying 80% completed 63 FTHCs given ongoing, Work 5 -25% Work order issued on 26/10/23 agreement executed on 7/11/23 ongoing, Work 6-100% completed . |
Kunnamkulam PH Sn - AE |
|
21 May 2024 |
PKG 1(Phase 1)-100 %Work completed. (Phase 2)Work1-15% Work started on 20/2/24 ongoing, Work 2 -50% Work started on 1/2/24 ongoing, Work 3-not started , Work 4- 60% pipe laying 80% completed 63 FTHCs given ongoing, Work 5 -25% Work order issued on 26/10/23 agreement executed on 7/11/23 ongoing, Work 6-100% completed . |
Kunnamkulam PH Sn - AE |
|
18 May 2024 |
PKG 1(Phase 1)-100 %Work completed. (Phase 2)Work1-15% ongoing, Work 2 -50% ongoing, Work 3-not started , Work 4-60% ongoing, Work 5 -25% ongoing, Work 6-65% ongoing, |
Thrissur PH Dn EE |
|
18 May 2024 |
PKG 1(Phase 1)-100 %Work completed. (Phase 2)Work1-15% ongoing, Work 2 -50% ongoing, Work 3-not started , Work 4-60% ongoing, Work 5 -25% ongoing, Work 6-65% ongoing, |
Kunnamkulam PH Sn - AE |
|
17 May 2024 |
PKG 1(Phase 1)-100 %Work completed. (Phase 2)Work1-15% ongoing, Work 2 -50% ongoing, Work 3-not started , Work 4-60% ongoing, Work 5 -25% ongoing, Work 6-65% ongoing, |
Thrissur PH Dn EE |
|
16 May 2024 |
PKG 1(Phase 1)-100 %Work completed. (Phase 2)Work1-15% ongoing, Work 2 -50% ongoing, Work 3-not started , Work 4-60% ongoing, Work 5 -25% ongoing, Work 6-65% ongoing, |
Kunnamkulam PH Sn - AE |
|
15 May 2024 |
PKG 1(Phase 1)-100 %Work completed. (Phase 2)Work1-15% ongoing, Work 2 -50% ongoing, Work 3-not started , Work 4-60% ongoing, Work 5 -25% ongoing, Work 6-65% ongoing, |
Kunnamkulam PH Sn - AE |
|
14 May 2024 |
PKG 1(Phase 1)-100 %Work completed. (Phase 2)Work1-15% ongoing, Work 2 -50% ongoing, Work 3-not started , Work 4-60% ongoing, Work 5 -25% ongoing, Work 6-65% ongoing, |
Kunnamkulam PH Sn - AE |
|
13 May 2024 |
PKG 1(Phase 1)-100 %Work completed. (Phase 2)Work1-15% ongoing, Work 2 -50% ongoing, Work 3-not started , Work 4-60% ongoing, Work 5 -25% ongoing, Work 6-65% ongoing, |
Kunnamkulam PH Sn - AE |
|
10 May 2024 |
PKG 1(Phase 1)-100 %Work completed. (Phase 2)Work1-15% ongoing, Work 2 -50% ongoing, Work 3-not started , Work 4-60% ongoing, Work 5 -25% ongoing, Work 6-65% ongoing, |
Thrissur PH Dn EE |
|