Jal Jeevan Mission (JJM)-Laying pipe lines for supply improvement in Kattakambal Panchayath - Phase 2- SLSSC-5th-Part-1-Pipeline Work

Project Jal Jeevan Mission (JJM)-Laying pipe lines for supply improvement in Kattakambal Panchayath - Phase 2- SLSSC-5th-Part-1-Pipeline Work
Project Code TCRJJM022213572
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission (JJM)-Laying pipe lines for supply improvement in Kattakambal Panchayath - Phase 2- SLSSC-5th-Part-1-Pipeline Work
Status On-going
District Thrissur
Executing Office Thrissur PH Dn
AS Amount (Rs) 275000000
AS Number G.O.(Rt)No.134/2022/WRD Dated,Thiruvananthapuram, 23-02-2022
TS Amount (Rs) 5090000
TS Number WRD/KWA-CE(CR)/EST_TS/14142/2022_26_1_1
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 24972
Capacity in MLD 33.00
Actual Project Completion Date Date is not specified
Coverage Kattakambal Panchayath
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Jal Jeevan Mission (JJM)-Laying pipelines for supply improvement in Kattakambal panchayath-250mm Dia DI K9 Kattakampal village office to Chirakkal centre-General Civil Work-1 Kunnamkulam Sn
2 Jal Jeevan Mission (JJM)-Laying pipe lines for supply improvement in kattakambal panchayath-additinal work VI-Road restoration works -Chirakkal Centre to Pengamuk Road,chirakkal centre to Vaykadavu Road at kattakambal panchayath - Supplying and laying 110mm PVC pipe and 90mm PVC Pipe at Karamukku road -General Civil Work Kunnamkulam Sn
3 Jal Jeevan Mission (JJM)-Laying pipe lines for supply improvement in Kattakambal Panchayath - Phase 2- SLSSC-5th-Part-1-Pipeline Work Kunnamkulam Sn
4 Jal Jeevan Mission (JJM)-Laying pipelines for supply improvement in Kattakambal panchayath work II-250mm Dia DI K9 Kattakampal - kurissu to Pazhanji church - General Civil Work Kunnamkulam Sn
5 Jal Jeevan Mission (JJM)-Laying pipelines for supply improvement in Kattakambal panchayath work III-200mm Dia K9 Kattkampal - pazhanji church to pazhanji school ground-General Civil Work Kunnamkulam Sn
6 Jal Jeevan Mission (JJM)-Laying pipelines for supply improvement in Kattakambal panchayath -Work IV-Providing FHTCs and Supplying & Laying 160mm & 110mm Dia. PVC pipe Pazhanji church to Karadikkunnu ,Pazhanji adakka market to Pattithadam Pazhanji school ground to Jerusalem centre ,Pazhanji school ground to Ayinoor and Colony roads -General Civil Work Kunnamkulam Sn
7 Jal Jeevan Mission (JJM)-Laying Pipe lines for supply improvement in Kattakambal Panchayath-Work V-Supplying and Laying 200mm DI K9 pipe and 160mm PVC Pipe from Chirakkal Centre to Pengamuk Road,chirakkal centre to Vaykadavu Road-General Civil Work Kunnamkulam Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
25 Jun 2024 PKG 1(Phase 1)-100 %Work completed. (Phase 2)Work1-15% Work started on 20/2/24 ongoing, Work 2 -50% Work started on 1/2/24 ongoing, Work 3-not started , Work 4- pipe laying 80% completed 63 FTHCs given ongoing, Work 5 -25% Work order issued on 26/10/23 agreement executed on 7/11/23 ongoing, Work 6-100% completed . Kunnamkulam PH Sn - AE
24 Jun 2024 PKG 1(Phase 1)-100 %Work completed. (Phase 2)Work1-15% Work started on 20/2/24 ongoing, Work 2 -50% Work started on 1/2/24 ongoing, Work 3-not started , Work 4- pipe laying 80% completed 63 FTHCs given ongoing, Work 5 -25% Work order issued on 26/10/23 agreement executed on 7/11/23 ongoing, Work 6-100% completed . Kunnamkulam PH Sn - AE
22 Jun 2024 PKG 1(Phase 1)-100 %Work completed. (Phase 2)Work1-15% Work started on 20/2/24 ongoing, Work 2 -50% Work started on 1/2/24 ongoing, Work 3-not started , Work 4- pipe laying 80% completed 63 FTHCs given ongoing, Work 5 -25% Work order issued on 26/10/23 agreement executed on 7/11/23 ongoing, Work 6-100% completed . Kunnamkulam PH Sn - AE
21 Jun 2024 PKG 1(Phase 1)-100 %Work completed. (Phase 2)Work1-15% Work started on 20/2/24 ongoing, Work 2 -50% Work started on 1/2/24 ongoing, Work 3-not started , Work 4- pipe laying 80% completed 63 FTHCs given ongoing, Work 5 -25% Work order issued on 26/10/23 agreement executed on 7/11/23 ongoing, Work 6-100% completed . Thrissur PH Dn EE
20 Jun 2024 PKG 1(Phase 1)-100 %Work completed. (Phase 2)Work1-15% Work started on 20/2/24 ongoing, Work 2 -50% Work started on 1/2/24 ongoing, Work 3-not started , Work 4- pipe laying 80% completed 63 FTHCs given ongoing, Work 5 -25% Work order issued on 26/10/23 agreement executed on 7/11/23 ongoing, Work 6-100% completed . Kunnamkulam PH Sn - AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 20/01/2023
Scheduled date of Completion of the Project 19 Apr 2023
Expected date of Completion 30/06/2024

Processing Dates

AS Date 23 Feb 2022
TS Date 26 Dec 2022

Other details

Project Officers View