Overall Project Status

Status Date Overall Project Status Project Officer Contact
07 Jun 2024 PKG 1(Phase 1)-100 %Work completed. (Phase 2)Work1-15% Work started on 20/2/24 ongoing, Work 2 -50% Work started on 1/2/24 ongoing, Work 3-not started , Work 4- 60% pipe laying 80% completed 63 FTHCs given ongoing, Work 5 -25% Work order issued on 26/10/23 agreement executed on 7/11/23 ongoing, Work 6-100% completed . Thrissur PH Dn EE
06 Jun 2024 PKG 1(Phase 1)-100 %Work completed. (Phase 2)Work1-15% Work started on 20/2/24 ongoing, Work 2 -50% Work started on 1/2/24 ongoing, Work 3-not started , Work 4- 60% pipe laying 80% completed 63 FTHCs given ongoing, Work 5 -25% Work order issued on 26/10/23 agreement executed on 7/11/23 ongoing, Work 6-100% completed . Kunnamkulam PH Sn - AE
05 Jun 2024 PKG 1(Phase 1)-100 %Work completed. (Phase 2)Work1-15% Work started on 20/2/24 ongoing, Work 2 -50% Work started on 1/2/24 ongoing, Work 3-not started , Work 4- 60% pipe laying 80% completed 63 FTHCs given ongoing, Work 5 -25% Work order issued on 26/10/23 agreement executed on 7/11/23 ongoing, Work 6-100% completed . Thrissur PH Dn EE
04 Jun 2024 PKG 1(Phase 1)-100 %Work completed. (Phase 2)Work1-15% Work started on 20/2/24 ongoing, Work 2 -50% Work started on 1/2/24 ongoing, Work 3-not started , Work 4- 60% pipe laying 80% completed 63 FTHCs given ongoing, Work 5 -25% Work order issued on 26/10/23 agreement executed on 7/11/23 ongoing, Work 6-100% completed . Kunnamkulam PH Sn - AE
03 Jun 2024 PKG 1(Phase 1)-100 %Work completed. (Phase 2)Work1-15% Work started on 20/2/24 ongoing, Work 2 -50% Work started on 1/2/24 ongoing, Work 3-not started , Work 4- 60% pipe laying 80% completed 63 FTHCs given ongoing, Work 5 -25% Work order issued on 26/10/23 agreement executed on 7/11/23 ongoing, Work 6-100% completed . Kunnamkulam PH Sn - AE
30 May 2024 PKG 1(Phase 1)-100 %Work completed. (Phase 2)Work1-15% Work started on 20/2/24 ongoing, Work 2 -50% Work started on 1/2/24 ongoing, Work 3-not started , Work 4- 60% pipe laying 80% completed 63 FTHCs given ongoing, Work 5 -25% Work order issued on 26/10/23 agreement executed on 7/11/23 ongoing, Work 6-100% completed . Kunnamkulam PH Sn - AE
29 May 2024 PKG 1(Phase 1)-100 %Work completed. (Phase 2)Work1-15% Work started on 20/2/24 ongoing, Work 2 -50% Work started on 1/2/24 ongoing, Work 3-not started , Work 4- 60% pipe laying 80% completed 63 FTHCs given ongoing, Work 5 -25% Work order issued on 26/10/23 agreement executed on 7/11/23 ongoing, Work 6-100% completed . Kunnamkulam PH Sn - AE
28 May 2024 PKG 1(Phase 1)-100 %Work completed. (Phase 2)Work1-15% Work started on 20/2/24 ongoing, Work 2 -50% Work started on 1/2/24 ongoing, Work 3-not started , Work 4- 60% pipe laying 80% completed 63 FTHCs given ongoing, Work 5 -25% Work order issued on 26/10/23 agreement executed on 7/11/23 ongoing, Work 6-100% completed . Thrissur PH Dn EE
27 May 2024 PKG 1(Phase 1)-100 %Work completed. (Phase 2)Work1-15% Work started on 20/2/24 ongoing, Work 2 -50% Work started on 1/2/24 ongoing, Work 3-not started , Work 4- 60% pipe laying 80% completed 63 FTHCs given ongoing, Work 5 -25% Work order issued on 26/10/23 agreement executed on 7/11/23 ongoing, Work 6-100% completed . Kunnamkulam PH Sn - AE
24 May 2024 PKG 1(Phase 1)-100 %Work completed. (Phase 2)Work1-15% Work started on 20/2/24 ongoing, Work 2 -50% Work started on 1/2/24 ongoing, Work 3-not started , Work 4- 60% pipe laying 80% completed 63 FTHCs given ongoing, Work 5 -25% Work order issued on 26/10/23 agreement executed on 7/11/23 ongoing, Work 6-100% completed . Kunnamkulam PH Sn - AE