Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
09 May 2024 | PKG 1(Phase 1)-100 %Work completed. (Phase 2)Work1-15% ongoing,Work 2 -50% ongoing,Work 3-not started ,Work 4-60% ongoing,Work 5 -25% ongoing,Work 6-65% ongoing, | Kunnamkulam PH Sn - AE | |
08 May 2024 | PKG 1(Phase 1)-100 %Work completed. (Phase 2)Work1-15% ongoing,Work 2 -50% ongoing,Work 3-not started ,Work 4-60% ongoing,Work 5 -25% ongoing,Work 6-65% ongoing, | Kunnamkulam PH Sn - AE | |
08 May 2024 | Completed | Kunnamkulam PH Sn - AE | |
06 May 2024 | PKG 1-Work order issued on 20/01/2023 and Agreement executed. 97 % completed. Work Ongoing, Pipe work laying work completed. Road Restoration work progressing. Other pkg- work going on. | Kunnamkulam PH Sn - AE | |
04 May 2024 | PKG 1-Work order issued on 20/01/2023 and Agreement executed. 97 % completed. Work Ongoing, Pipe work laying work completed. Road Restoration work progressing. Other pkg- work going on. | Thrissur PH Dn EE | |
03 May 2024 | PKG 1-Work order issued on 20/01/2023 and Agreement executed. 97 % completed. Work Ongoing, Pipe work laying work completed. Road Restoration work progressing. Other pkg- work going on. | Thrissur PH Dn EE | |
02 May 2024 | PKG 1-Work order issued on 20/01/2023 and Agreement executed. 97 % completed. Work Ongoing, Pipe work laying work completed. Road Restoration work progressing. Other pkg- work going on. | Thrissur PH Dn EE | |
29 Apr 2024 | PKG 1-Work order issued on 20/01/2023 and Agreement executed. 97 % completed. Work Ongoing, Pipe work laying work completed. Road Restoration work progressing. Other pkg- work going on. | Kunnamkulam PH Sn - AE | |
29 Apr 2024 | PKG 1-Work order issued on 20/01/2023 and Agreement executed. 97 % completed. Work Ongoing, Pipe work laying work completed. Road Restoration work progressing. Other pkg- work going on. | Thrissur PH Dn EE | |
27 Apr 2024 | PKG 1-Work order issued on 20/01/2023 and Agreement executed. 97 % completed. Work Ongoing, Pipe work laying work completed. Road Restoration work progressing. Other pkg- work going on. | Thrissur PH Dn EE |