Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
22 Feb 2024 | PKG 1-Work order issued on 20/01/2023 and Agreement executed. 97 % completed. Work Ongoing, Pipe work laying work completed. Road Restoration work progressing. Other pkg- work going on | Kunnamkulam PH Sn - AE | |
21 Feb 2024 | PKG 1-Work order issued on 20/01/2023 and Agreement executed. 97 % completed. Work Ongoing, Pipe work laying work completed. Road Restoration work progressing. Other pkg- work going on | Kunnamkulam PH Sn - AE | |
20 Feb 2024 | PKG 1-Work order issued on 20/01/2023 and Agreement executed. 97 % completed. Work Ongoing, Pipe work laying work completed. Road Restoration work progressing. Other pkg- work going on | Kunnamkulam PH Sn - AE | |
19 Feb 2024 | PKG 1-Work order issued on 20/01/2023 and Agreement executed. 97 % completed. Work Ongoing, Pipe work laying work completed. Road Restoration work progressing. Other pkg- work going on | Thrissur PH Dn EE | |
17 Feb 2024 | PKG 1-Work order issued on 20/01/2023 and Agreement executed. 97 % completed. Work Ongoing, Pipe work laying work completed. Road Restoration work progressing. Other pkg- work going on | Kunnamkulam PH Sn - AE | |
15 Feb 2024 | PKG 1-Work order issued on 20/01/2023 and Agreement executed. 97 % completed. Work Ongoing, Pipe work laying work completed. Road Restoration work progressing. Other pkg- work going on | Kunnamkulam PH Sn - AE | |
13 Feb 2024 | PKG 1-Work order issued on 20/01/2023 and Agreement executed. 97 % completed. Work Ongoing, Pipe work laying work completed. Road Restoration work progressing. Other pkg- work going on | Kunnamkulam PH Sn - AE | |
12 Feb 2024 | PKG 1-Work order issued on 20/01/2023 and Agreement executed. 97 % completed. Work Ongoing, Pipe work laying work completed. Road Restoration work progressing. Other pkg- work going on | Kunnamkulam PH Sn - AE | |
08 Feb 2024 | PKG 1-Work order issued on 20/01/2023 and Agreement executed. 97 % completed. Work Ongoing, Pipe work laying work completed. Road Restoration work progressing. Other pkg- work going on | Kunnamkulam PH Sn - AE | |
06 Feb 2024 | PKG 1-Work order issued on 20/01/2023 and Agreement executed. 97 % completed. Work Ongoing, Pipe work laying work completed. Road Restoration work progressing. Other pkg- work going on | Kunnamkulam PH Sn - AE |