Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
02 Sep 2023 | pipe laying work in progress | Kollam WS Sn 3 - AE | |
01 Sep 2023 | Pipe laying work in progress. | Kollam WS Sn 3 - AE | |
26 Aug 2023 | Pipe laying work in progress. | Kollam WS Sn 3 - AE | |
22 Aug 2023 | 400mm DI pipe laying work in progress. | Kollam WS Sn 3 - AE | |
18 Aug 2023 | 125 mm HDPE pipe laying work at NH 208 Kerlapuram to Karikkode work in progress. | Kollam WS Sn 3 - AE | |
11 Aug 2023 | 125 mm HDPE pipe laying work at NH 208 Kerlapuram to Karikkode work in progress. | Kollam WS Sn 3 - AE | |
07 Aug 2023 | 125 mm HDPE pipe laying work at NH 208 Kerlapuram to Karikkode work in progress. | Kollam WS Sn 3 - AE | |
04 Aug 2023 | 125mm HDPE pipe and 200 mm DI pipe laying work in progress. | Kollam WS Sn 3 - AE | |
31 Jul 2023 | 125mm HDPE pipe and 200 mm DI pipe laying work in progress. | Kollam WS Sn 3 - AE | |
27 Jul 2023 | 110 PE pipe laying work in progress. | Kollam WS Sn 3 - AE |