Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
13 Oct 2023 | pipe laying work in progress. | Kollam WS Sn 3 - AE | |
10 Oct 2023 | 125mm HDPE pipe laying work in NH karicode to keralapuram in progress | Kollam WS Sn 3 - AE | |
06 Oct 2023 | 125mm HDPE pipe laying work in NH karicode to keralapuram in progress and 125mm HDPE pipe laying work in PWD road Keralapuram to Kovilmukku road in progress. | Kollam WS Sn 3 - AE | |
04 Oct 2023 | hdpe pipe laying work in progress. | Kollam WS Sn 3 - AE | |
29 Sep 2023 | DI pipe laying work in progress | Kollam WS Sn 3 - AE | |
26 Sep 2023 | HDPE pipe laying work in progress. | Kollam WS Sn 3 - AE | |
19 Sep 2023 | 2nd level column concrete done. | Kollam WS Sn 3 - AE | |
16 Sep 2023 | HDPE pipe laying work in progress. | Kollam WS Sn 3 - AE | |
12 Sep 2023 | HDPE pipe laying work in progress. | Kollam WS Sn 3 - AE | |
07 Sep 2023 | pipe laying work in progress | Kollam WS Sn 3 - AE |